What is the length of the critical path for this project? (A) 9 days (B) 14 days (C) 18 days (D) 27 days - HSC - SSCE Business Studies - Question 14 - 2015 - Paper 1

Question icon

Question 14

What-is-the-length-of-the-critical-path-for-this-project?--(A)-9-days-(B)-14-days-(C)-18-days-(D)-27-days-HSC-SSCE Business Studies-Question 14-2015-Paper 1.png

What is the length of the critical path for this project? (A) 9 days (B) 14 days (C) 18 days (D) 27 days

Worked Solution & Example Answer:What is the length of the critical path for this project? (A) 9 days (B) 14 days (C) 18 days (D) 27 days - HSC - SSCE Business Studies - Question 14 - 2015 - Paper 1

Step 1

Calculate the critical path length

96%

114 rated

Answer

To determine the length of the critical path, we need to analyze the project activities and their dependencies. The critical path is the longest duration path through a project, determining the shortest time to complete the project.

  1. List all activities: Identify all activities involved in the project along with their durations and dependencies.
  2. Create a network diagram: Visualize the activities and their interdependencies to see how they relate to each other.
  3. Calculate paths: Measure the total time for each possible path through the network.
  4. Identify the longest path: The critical path is the one with the maximum total duration. In this case, based on the provided options, the length of the critical path is 18 days, which corresponds to option (C).