If activity EC is delayed and takes 6 days, by how long will the project be delayed?
(A) 0 days
(B) 3 days
(C) 6 days
(D) 17 days - HSC - SSCE Business Studies - Question 15 - 2015 - Paper 1
Question 15
If activity EC is delayed and takes 6 days, by how long will the project be delayed?
(A) 0 days
(B) 3 days
(C) 6 days
(D) 17 days
Worked Solution & Example Answer:If activity EC is delayed and takes 6 days, by how long will the project be delayed?
(A) 0 days
(B) 3 days
(C) 6 days
(D) 17 days - HSC - SSCE Business Studies - Question 15 - 2015 - Paper 1
Step 1
Determine the impact of the delay
96%
114 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
When an activity in a project is delayed, its duration directly influences the overall project timeline. In this case, activity EC is delayed by 6 days.
To assess the overall project delay, we need to consider the position of activity EC within the project schedule, particularly whether it is on the critical path or not.
Step 2
Critical path analysis
99%
104 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
If activity EC is part of the critical path, the total project duration would be extended by 6 days due to the delay. Conversely, if it is not on the critical path, then the project may not be delayed.
Assuming that EC is indeed on the critical path, the project will be delayed by exactly 6 days.
Step 3
Select the correct answer
96%
101 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
Given that the activity is delayed by 6 days, the correct answer is (C) 6 days.