If activity EC is delayed and takes 6 days, by how long will the project be delayed?
(A) 0 days
(B) 3 days
(C) 6 days
(D) 17 days - HSC - SSCE Business Studies - Question 15 - 2015 - Paper 1
Question 15
If activity EC is delayed and takes 6 days, by how long will the project be delayed?
(A) 0 days
(B) 3 days
(C) 6 days
(D) 17 days
Worked Solution & Example Answer:If activity EC is delayed and takes 6 days, by how long will the project be delayed?
(A) 0 days
(B) 3 days
(C) 6 days
(D) 17 days - HSC - SSCE Business Studies - Question 15 - 2015 - Paper 1
Step 1
Identify the delay caused by activity EC
96%
114 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
Activity EC is directly linked to the project's timeline. If it is delayed and takes an additional 6 days, then its impact must be assessed in terms of how it affects the overall project duration.
Step 2
Determine the critical path and dependencies
99%
104 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
Identify if activity EC is on the critical path. If it is, any delay will contribute directly to the project's overall delay. If it is not on the critical path, the delay might not affect the project duration.
Step 3
Conclusion regarding the project delay
96%
101 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
Since activity EC is delayed by 6 days and is likely on the critical path, the overall project will be delayed by a corresponding 6 days.