If activity EC is delayed and takes 6 days, by how long will the project be delayed? (A) 0 days (B) 3 days (C) 6 days (D) 17 days - HSC - SSCE Business Studies - Question 15 - 2015 - Paper 1

Question icon

Question 15

If-activity-EC-is-delayed-and-takes-6-days,-by-how-long-will-the-project-be-delayed?--(A)-0-days-(B)-3-days-(C)-6-days-(D)-17-days-HSC-SSCE Business Studies-Question 15-2015-Paper 1.png

If activity EC is delayed and takes 6 days, by how long will the project be delayed? (A) 0 days (B) 3 days (C) 6 days (D) 17 days

Worked Solution & Example Answer:If activity EC is delayed and takes 6 days, by how long will the project be delayed? (A) 0 days (B) 3 days (C) 6 days (D) 17 days - HSC - SSCE Business Studies - Question 15 - 2015 - Paper 1

Step 1

Identify the delay caused by activity EC

96%

114 rated

Answer

Activity EC is directly linked to the project's timeline. If it is delayed and takes an additional 6 days, then its impact must be assessed in terms of how it affects the overall project duration.

Step 2

Determine the critical path and dependencies

99%

104 rated

Answer

Identify if activity EC is on the critical path. If it is, any delay will contribute directly to the project's overall delay. If it is not on the critical path, the delay might not affect the project duration.

Step 3

Conclusion regarding the project delay

96%

101 rated

Answer

Since activity EC is delayed by 6 days and is likely on the critical path, the overall project will be delayed by a corresponding 6 days.