Which of the following are common characteristics of a critical path analysis?
A - HSC - SSCE Business Studies - Question 18 - 2024 - Paper 1
Question 18
Which of the following are common characteristics of a critical path analysis?
A. What tasks need to be done, how long they take, delivery timing
B. What tasks need... show full transcript
Worked Solution & Example Answer:Which of the following are common characteristics of a critical path analysis?
A - HSC - SSCE Business Studies - Question 18 - 2024 - Paper 1
Step 1
Identify common characteristics of a critical path analysis
96%
114 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
Critical path analysis is a project management technique used to determine the longest sequence of dependent tasks and to identify tasks that can be completed simultaneously. The main characteristics typically analyzed include:
Tasks Identification: Understanding which tasks need to be accomplished.
Duration Estimation: Determining how long each task will take.
Order of Tasks: Identifying the necessary sequence or order for tasks to ensure proper workflow.
Based on the options provided:
Option A focuses on delivery timing but lacks emphasis on the necessary order of tasks.
Option B addresses the identification of tasks, their duration, and their necessary order, making it the most relevant choice.
Option C discusses simultaneous tasks but lacks comprehensive detail regarding duration or order.
Option D, although touching on simultaneity, diverts from key features of critical path analysis, focusing too much on components.