Photo AI

What is the length of the critical path for this project? (A) 9 days (B) 14 days (C) 18 days (D) 27 days - HSC - SSCE Business Studies - Question 14 - 2015 - Paper 1

Question icon

Question 14

What-is-the-length-of-the-critical-path-for-this-project?--(A)-9-days--(B)-14-days--(C)-18-days--(D)-27-days-HSC-SSCE Business Studies-Question 14-2015-Paper 1.png

What is the length of the critical path for this project? (A) 9 days (B) 14 days (C) 18 days (D) 27 days

Worked Solution & Example Answer:What is the length of the critical path for this project? (A) 9 days (B) 14 days (C) 18 days (D) 27 days - HSC - SSCE Business Studies - Question 14 - 2015 - Paper 1

Step 1

Determine the Critical Path Length

96%

114 rated

Answer

To find the length of the critical path, one must analyze the project's tasks, identify dependencies, and calculate the total time taken for each sequence of tasks. The critical path is the longest duration path through the project, which determines the minimum time needed to complete the project.

Upon analysis, we find that the critical path for this project has a total duration of 18 days.

Step 2

Select the Correct Option

99%

104 rated

Answer

Based on the calculations, the correct answer is (C) 18 days.

Join the SSCE students using SimpleStudy...

97% of Students

Report Improved Results

98% of Students

Recommend to friends

100,000+

Students Supported

1 Million+

Questions answered

;