What is the length of the critical path for this project?
(A) 9 days
(B) 14 days
(C) 18 days
(D) 27 days - HSC - SSCE Business Studies - Question 14 - 2015 - Paper 1
Question 14
What is the length of the critical path for this project?
(A) 9 days
(B) 14 days
(C) 18 days
(D) 27 days
Worked Solution & Example Answer:What is the length of the critical path for this project?
(A) 9 days
(B) 14 days
(C) 18 days
(D) 27 days - HSC - SSCE Business Studies - Question 14 - 2015 - Paper 1
Step 1
Determine the Critical Path Length
96%
114 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
To find the length of the critical path, one must analyze the project's tasks, identify dependencies, and calculate the total time taken for each sequence of tasks. The critical path is the longest duration path through the project, which determines the minimum time needed to complete the project.
Upon analysis, we find that the critical path for this project has a total duration of 18 days.
Step 2
Select the Correct Option
99%
104 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
Based on the calculations, the correct answer is (C) 18 days.