What does a critical path identify?
(A) The lowest cost path to complete all tasks in a project
(B) The highest cost path to complete all tasks in a project
(C) The longest time required to complete all tasks in a project
(D) The shortest time required to complete all tasks in a project - HSC - SSCE Business Studies - Question 8 - 2013 - Paper 1
Question 8
What does a critical path identify?
(A) The lowest cost path to complete all tasks in a project
(B) The highest cost path to complete all tasks in a project
(C) The... show full transcript
Worked Solution & Example Answer:What does a critical path identify?
(A) The lowest cost path to complete all tasks in a project
(B) The highest cost path to complete all tasks in a project
(C) The longest time required to complete all tasks in a project
(D) The shortest time required to complete all tasks in a project - HSC - SSCE Business Studies - Question 8 - 2013 - Paper 1
Step 1
What does a critical path identify?
96%
114 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
The critical path in project management refers to the longest sequence of tasks that must be completed on time for the entire project to be finished on schedule. Therefore, it identifies the longest time required to complete all tasks in a project.
Correct Answer: (C) The longest time required to complete all tasks in a project.