The preparation of a meal requires the completion of all ten activities A to J - HSC - SSCE Mathematics Standard - Question 26 - 2020 - Paper 1
Question 26
The preparation of a meal requires the completion of all ten activities A to J. The network diagram shows the activities and their completion times in minutes.
(a) ... show full transcript
Worked Solution & Example Answer:The preparation of a meal requires the completion of all ten activities A to J - HSC - SSCE Mathematics Standard - Question 26 - 2020 - Paper 1
Step 1
What is the minimum time needed to prepare the meal?
96%
114 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
To determine the minimum time needed to prepare the meal, we analyze the network diagram by identifying all the paths from start to finish and calculating their total durations. The paths are:
A -> B -> D -> H -> J: 12 + 6 + 8 + 10 + 7 = 43 minutes
A -> C -> E -> H -> J: 12 + 8 + 20 + 10 + 7 = 57 minutes
B -> D -> E -> F -> H -> J: 0 + 8 + 20 + 10 + 7 = 45 minutes
A -> B -> E -> F -> H -> J: 12 + 6 + 20 + 10 + 7 = 55 minutes
After evaluating all paths, the minimum time required is found to be 46 minutes.
Step 2
List the activities which make up the critical path for this network.
99%
104 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
The activities that make up the critical path are:
C -> D -> E -> F -> H -> I
Step 3
Complete the table below, showing the earliest start time and float time for activities A and G.
96%
101 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!