Photo AI

The preparation of a meal requires the completion of all ten activities A to J - HSC - SSCE Mathematics Standard - Question 26 - 2020 - Paper 1

Question icon

Question 26

The-preparation-of-a-meal-requires-the-completion-of-all-ten-activities-A-to-J-HSC-SSCE Mathematics Standard-Question 26-2020-Paper 1.png

The preparation of a meal requires the completion of all ten activities A to J. The network diagram shows the activities and their completion times in minutes. (a) ... show full transcript

Worked Solution & Example Answer:The preparation of a meal requires the completion of all ten activities A to J - HSC - SSCE Mathematics Standard - Question 26 - 2020 - Paper 1

Step 1

What is the minimum time needed to prepare the meal?

96%

114 rated

Answer

To determine the minimum time needed to prepare the meal, we analyze the network diagram by identifying all the paths from start to finish and calculating their total durations. The paths are:

  1. A -> B -> D -> H -> J: 12 + 6 + 8 + 10 + 7 = 43 minutes
  2. A -> C -> E -> H -> J: 12 + 8 + 20 + 10 + 7 = 57 minutes
  3. B -> D -> E -> F -> H -> J: 0 + 8 + 20 + 10 + 7 = 45 minutes
  4. A -> B -> E -> F -> H -> J: 12 + 6 + 20 + 10 + 7 = 55 minutes

After evaluating all paths, the minimum time required is found to be 46 minutes.

Step 2

List the activities which make up the critical path for this network.

99%

104 rated

Answer

The activities that make up the critical path are:

C -> D -> E -> F -> H -> I

Step 3

Complete the table below, showing the earliest start time and float time for activities A and G.

96%

101 rated

Answer

ActivityEarliest start time (minutes)Float time (minutes)
A012
G3615

Join the SSCE students using SimpleStudy...

97% of Students

Report Improved Results

98% of Students

Recommend to friends

100,000+

Students Supported

1 Million+

Questions answered

;