The network diagram shows the time needed for each step in order to complete a project - HSC - SSCE Mathematics Standard - Question 3 - 2022 - Paper 1

Question icon

Question 3

The-network-diagram-shows-the-time-needed-for-each-step-in-order-to-complete-a-project-HSC-SSCE Mathematics Standard-Question 3-2022-Paper 1.png

The network diagram shows the time needed for each step in order to complete a project. 3 3 C, 13 16 20 A, 3 --> D, 16 --> G, 1 2 0... show full transcript

Worked Solution & Example Answer:The network diagram shows the time needed for each step in order to complete a project - HSC - SSCE Mathematics Standard - Question 3 - 2022 - Paper 1

Step 1

What is the critical path to complete the project?

96%

114 rated

Answer

To determine the critical path, we first need to identify all possible paths from the start to the end of the project based on the network diagram:

  1. Path ACI: A (3) → C (13) → I (2) = 3 + 13 + 2 = 18
  2. Path ADG: A (3) → D (16) → G (1) = 3 + 16 + 1 = 20
  3. Path BEH: B (2) → E (9) → H (6) = 2 + 9 + 6 = 17
  4. Path BEFG: B (2) → E (9) → F (2) → G (1) = 2 + 9 + 2 + 1 = 14

Next, we will summarize the total times for each path:

  • ACI: 18
  • ADG: 20
  • BEH: 17
  • BEFG: 14

The critical path is the one with the longest duration, which is ADG with a total time of 20.