Photo AI

Using the data in the network diagram above, calculate the Earliest Start Times (EST) and Latest Finishing Times (LFT) for each activity and identify the critical path. - Edexcel - A-Level Business - Question 2 - 2017 - Paper 2

Question icon

Question 2

Using-the-data-in-the-network-diagram-above,-calculate-the-Earliest-Start-Times-(EST)-and-Latest-Finishing-Times-(LFT)-for-each-activity-and-identify-the-critical-path.----Edexcel-A-Level Business-Question 2-2017-Paper 2.png

Using the data in the network diagram above, calculate the Earliest Start Times (EST) and Latest Finishing Times (LFT) for each activity and identify the critical pa... show full transcript

Worked Solution & Example Answer:Using the data in the network diagram above, calculate the Earliest Start Times (EST) and Latest Finishing Times (LFT) for each activity and identify the critical path. - Edexcel - A-Level Business - Question 2 - 2017 - Paper 2

Step 1

Calculate the Earliest Start Times (EST)

96%

114 rated

Answer

  1. Activity A: Since it has no predecessor, EST = 0.
  2. Activity B: EST = 0 (A must finish before B can start).
  3. Activity C: EST = max(EST of A) = 0.
  4. Activity D: EST = max(EST of B) = 3.
  5. Activity E: EST = max(EST of C) = 3.
  6. Activity F: EST = max(EST of D) = 11.
  7. Activity G: EST = max(EST of E) = 14.
  8. Activity H: EST = max(EST of F and G) = 18.

Step 2

Calculate the Latest Finishing Times (LFT)

99%

104 rated

Answer

  1. Activity H: LFT = 18 (as it is the final activity).
  2. Activity F: LFT = LFT(H) = 18 - 5 = 13.
  3. Activity G: LFT = LFT(H) = 18 - 4 = 14.
  4. Activity D: LFT = LFT(F) = 13 - 3 = 10.
  5. Activity E: LFT = LFT(G) = 14 - 3 = 11.
  6. Activity B: LFT = 10 (as it depends on D).
  7. Activity C: LFT = 11 (as it depends on E).
  8. Activity A: LFT = min(LFT(B), LFT(C)) = 10.

Step 3

Identify the Critical Path

96%

101 rated

Answer

The critical path includes the activities that have the same EST and LFT. Here, the critical path is A → B → D → F → H, as these activities have no flexibility in their scheduling.

Join the A-Level students using SimpleStudy...

97% of Students

Report Improved Results

98% of Students

Recommend to friends

100,000+

Students Supported

1 Million+

Questions answered

;