Revision notes with simplified explanations to understand Critical Path Analysis quickly and effectively.
423+ students studying
đź”— A tool that uses network analysis to help project managers handle complex and time-sensitive operations.
đź”— The model can be used to identify the most efficient way to complete risky and complex projects. The model must contain the following:
EST of Task A is 0 months, as there are no tasks before it.
EST of Task B is 2 months (EST of 1 + duration of A)
EST of Task C is 6 months (EST of 2 + duration of B)
EST of Task D is 8 months (EST of 3 + duration of C)
EST of Task E is 11 months (EST of 4 + duration of D). The duration of D is chosen rather than the duration of C. This is because when calculating the EST with a branch, the largest number out of the two is taken.
LFT is calculated by looking right to left on the network diagram.
LFT of Task G is 15, as there are no tasks after it.
LFT of Task F is 14 (LFT of 7 – duration of G)
LFT of Task D is 10 (LFT of 5 – duration of E). The duration of E is chosen rather than F. This is because when calculating LFT with a branch, the smallest value out of the two is taken.
LFT of Task C is 10 (LFT of 14 – duration of F)
đź”— The duration of the activity can be extended or postponed but still allows the project to finish within the minimum time.
Pros:
Cons:
Enhance your understanding with flashcards, quizzes, and exams—designed to help you grasp key concepts, reinforce learning, and master any topic with confidence!
40 flashcards
Flashcards on Critical Path Analysis
Revise key concepts with interactive flashcards.
Try Business Flashcards4 quizzes
Quizzes on Critical Path Analysis
Test your knowledge with fun and engaging quizzes.
Try Business Quizzes29 questions
Exam questions on Critical Path Analysis
Boost your confidence with real exam questions.
Try Business Questions27 exams created
Exam Builder on Critical Path Analysis
Create custom exams across topics for better practice!
Try Business exam builder9 papers
Past Papers on Critical Path Analysis
Practice past papers to reinforce exam experience.
Try Business Past PapersDiscover More Revision Notes Related to Critical Path Analysis to Deepen Your Understanding and Improve Your Mastery
Join 500,000+ A-Level students using SimpleStudy...
Join Thousands of A-Level Students Using SimpleStudy to Learn Smarter, Stay Organized, and Boost Their Grades with Confidence!
Report Improved Results
Recommend to friends
Students Supported
Questions answered