Critical Path Analysis Simplified Revision Notes

Revision notes with simplified explanations to understand Critical Path Analysis quickly and effectively.

user avatar
user avatar
user avatar
user avatar
user avatar

343+ students studying

3.3.4 Critical Path Analysis

Critical path analysis

đź”— A tool that uses network analysis to help project managers handle complex and time-sensitive operations.

Function of the model

đź”— The model can be used to identify the most efficient way to complete risky and complex projects. The model must contain the following:

  • A list of all activities required to complete the project.
  • The time (duration) that each activity will take to complete.
  • The dependencies between the activities. The process determines which activities are 'critical' (on the longest path) and which activities are 'total float' (can be delayed without making the project longer).

The 3 components of network analysis

image

How to construct the network diagram

image image

Calculating EST

EST of Task A is 0 months, as there are no tasks before it.

EST of Task B is 2 months (EST of 1 + duration of A)

EST of Task C is 6 months (EST of 2 + duration of B)

EST of Task D is 8 months (EST of 3 + duration of C)

EST of Task E is 11 months (EST of 4 + duration of D). The duration of D is chosen rather than the duration of C. This is because when calculating the EST with a branch, the largest number out of the two is taken.

image

Calculating LFT

LFT is calculated by looking right to left on the network diagram.

LFT of Task G is 15, as there are no tasks after it.

LFT of Task F is 14 (LFT of 7 – duration of G)

LFT of Task D is 10 (LFT of 5 – duration of E). The duration of E is chosen rather than F. This is because when calculating LFT with a branch, the smallest value out of the two is taken.

LFT of Task C is 10 (LFT of 14 – duration of F)

image

Float

đź”— The duration of the activity can be extended or postponed but still allows the project to finish within the minimum time.

Formula:LFT–EST–DurationFormula: LFT – EST – Duration

Pros and Cons of CPA

Pros:

  • Reduces risks and costs of a project.
  • Helps identify which activities have 'float', therefore allows better resource allocation.
  • Both are a decision-making and planning tool, which saves time and costs in making both.

Cons:

  • Largely based on estimates and assumptions, which decreases reliability.
  • Resources may not be as flexible as suggested by the diagram, making them harder to allocate from 'float activities.'
  • Too many activities make the diagram too complicated. Takes time to make
Books

Only available for registered users.

Sign up now to view the full note, or log in if you already have an account!

500K+ Students Use These Powerful Tools to Master Critical Path Analysis

Enhance your understanding with flashcards, quizzes, and exams—designed to help you grasp key concepts, reinforce learning, and master any topic with confidence!

40 flashcards

Flashcards on Critical Path Analysis

Revise key concepts with interactive flashcards.

Try Business Flashcards

4 quizzes

Quizzes on Critical Path Analysis

Test your knowledge with fun and engaging quizzes.

Try Business Quizzes

29 questions

Exam questions on Critical Path Analysis

Boost your confidence with real exam questions.

Try Business Questions

27 exams created

Exam Builder on Critical Path Analysis

Create custom exams across topics for better practice!

Try Business exam builder

21 papers

Past Papers on Critical Path Analysis

Practice past papers to reinforce exam experience.

Try Business Past Papers

Other Revision Notes related to Critical Path Analysis you should explore

Discover More Revision Notes Related to Critical Path Analysis to Deepen Your Understanding and Improve Your Mastery

96%

114 rated

Decision-making Techniques

Quantitative Sales Forecasting

user avatar
user avatar
user avatar
user avatar
user avatar

367+ studying

185KViews

96%

114 rated

Decision-making Techniques

Investment Appraisal

user avatar
user avatar
user avatar
user avatar
user avatar

355+ studying

186KViews

96%

114 rated

Decision-making Techniques

Decision Trees

user avatar
user avatar
user avatar
user avatar
user avatar

278+ studying

193KViews
Load more notes

Join 500,000+ A-Level students using SimpleStudy...

Join Thousands of A-Level Students Using SimpleStudy to Learn Smarter, Stay Organized, and Boost Their Grades with Confidence!

97% of Students

Report Improved Results

98% of Students

Recommend to friends

500,000+

Students Supported

50 Million+

Questions answered