Photo AI

3.1 Choose a cost category from COLUMN B that matches the example in COLUMN A - NSC Accounting - Question 3 - 2024 - Paper 2

Question icon

Question 3

3.1-Choose-a-cost-category-from-COLUMN-B-that-matches-the-example-in-COLUMN-A-NSC Accounting-Question 3-2024-Paper 2.png

3.1 Choose a cost category from COLUMN B that matches the example in COLUMN A. Write only the letter (A–D) next to the question numbers (3.1.1 to 3.1.3) in the ANSWE... show full transcript

Worked Solution & Example Answer:3.1 Choose a cost category from COLUMN B that matches the example in COLUMN A - NSC Accounting - Question 3 - 2024 - Paper 2

Step 1

3.1.1 Delivery expenses

96%

114 rated

Answer

B (selling and distribution)

Step 2

3.1.2 Office stationery

99%

104 rated

Answer

D (administration)

Step 3

3.1.3 Salary of the factory supervisor

96%

101 rated

Answer

A (factory overhead)

Step 4

3.2 Calculate the correct factory overhead cost

98%

120 rated

Answer

To calculate the correct factory overhead cost, we need to consider the following adjustments:

  1. Water and Electricity Expense Adjustment:

    Let the total water and electricity expense be represented as XX. Then, the portion allocated to factory overhead is: 0.75X0.75X The portion allocated to administration is: 0.25X=R9,6000.25X = R9,600 Solving for XX gives: X=R9,600imes4=R38,400X = R9,600 imes 4 = R38,400 Therefore, the factory portion becomes: 0.75imesR38,400=R28,8000.75 imes R38,400 = R28,800

  2. Rent Expense Adjustment:

    • Total rent expense recorded = R142,800
    • Factory allocation based on floor area ratio: ext{Factory share} = R142,800 imes rac{220}{420} = R68,800
  3. Insurance Expense Adjustment:

    • Original allocation = R48,000, adjusted based on correct ratio: ext{Correct factory share} = R48,000 imes rac{5}{7} = R34,285.71

Now summing all together:

Factory overhead cost:

  • Original = R258,200 (incorrect)
  • Adjusted = R28,800 (water) + R68,800 (rent) + R34,285.71 (insurance) = R131,885.71

Total factory overhead cost becomes: extTotal=R131,885.71+R38,400+R9,600=R223,885.71 ext{Total} = R131,885.71 + R38,400 + R9,600 = R223,885.71

Step 5

3.3 Complete the Production Cost Statement

97%

117 rated

Answer

To complete the production cost statement:

  1. Direct Material Cost:

    Issued to factory: extTotalfabric=70,000m59,500m=10,500m ext{Total fabric} = 70,000 m - 59,500 m = 10,500 m Thus, total cost of issued material = Cost per meter of last purchase: 59,500imesR12.20=R726,90059,500 imes R12.20 = R726,900

  2. Work-in-Progress: Latest Work-in-progress per indicated = R30,700.

  3. Calculation of Prime Cost:

    extPrimeCost=extDirectMaterialCost+extDirectLabourCost ext{Prime Cost} = ext{Direct Material Cost} + ext{Direct Labour Cost}

  4. Total Factory Overhead Costs: As previously calculated: R223,885.71.

  5. Final Calculation of Total Manufacturing Cost:

    extTotal=extPrimeCost+extFactoryOverheads ext{Total} = ext{Prime Cost} + ext{Factory Overheads}

  6. Continue with calculating Work-in-Progress to complete the statement.

Join the NSC students using SimpleStudy...

97% of Students

Report Improved Results

98% of Students

Recommend to friends

100,000+

Students Supported

1 Million+

Questions answered

;