1.1 Start the drawing from corner A, as indicated in the bottom left-hand corner of the sheet - NSC Civil Technology Civil Services - Question 1 - 2017 - Paper 1

Question icon

Question 1

1.1-Start-the-drawing-from-corner-A,-as-indicated-in-the-bottom-left-hand-corner-of-the-sheet-NSC Civil Technology Civil Services-Question 1-2017-Paper 1.png

1.1 Start the drawing from corner A, as indicated in the bottom left-hand corner of the sheet. 1.2 There are several rights that the building on the outside side of... show full transcript

Worked Solution & Example Answer:1.1 Start the drawing from corner A, as indicated in the bottom left-hand corner of the sheet - NSC Civil Technology Civil Services - Question 1 - 2017 - Paper 1

Step 1

1.1 Start the drawing from corner A, as indicated in the bottom left-hand corner of the sheet.

96%

114 rated

Answer

To begin the drawing, ensure that corner A is positioned correctly on the sheet. Make sure to follow the specified dimensions outlined in the exam question.

Step 2

1.2 There are several rights that the building on the outside side of the house.

99%

104 rated

Answer

Identify and mark the rights associated with the building's external features. Highlight any necessary points of interest or regulatory requirements as per code.

Step 3

1.3 Washthe roof for open-plan/kitchenette room as indicated.

96%

101 rated

Answer

Create a schematic to represent the roof over the open-plan kitchen area. Utilize appropriate roofing symbols to convey design intent.

Step 4

1.4 The external walls are rather walls, as well as the interior wooden parts of the house.

98%

120 rated

Answer

Clearly define the external walls, ensuring to note the materials used, which could include bricks or wood, as well as their placements on the drawing.

Step 5

1.5 The vertical right of the building, keeping it as flat as possible, and extended for the residential walls and flooring system.

97%

117 rated

Answer

Outline the vertical elements of the building. Make sure to address how these support the structure, possibly detailing any load-bearing elements.

Step 6

1.6 The correct symbol for the gabled roof is a square symbol drawn in the bottom left corner.

97%

121 rated

Answer

Represent the gabled roof using the specified square symbol. Ensure it's correctly placed in relation to the rest of the drawing.

Step 7

1.7 The construction symbols include the openings for the windows that are part of the kitchen hut and the wall and those around it, as indicated in the right corner of the dra.

96%

114 rated

Answer

Incorporate standard construction symbols for windows and other features in the kitchen area. Position them accurately according to the indicated plan.

Step 8

1.8 Correctly positioned and determined.

99%

104 rated

Answer

Mark the positions of all elements with precision, adhering strictly to the measurements and guidelines outlined in the exam document.

Step 9

1.9 Draw the concrete floor plan based on the indicated width and the correct place as illustrated.

96%

101 rated

Answer

Develop the concrete floor plan by following the specified dimensions. Illustrate the arrangement to ensure clarity.

Step 10

1.10 The design must align with the rules of the architectural structure.

98%

120 rated

Answer

Evaluate the design against architectural standards ensuring compliance with local building codes.

Step 11

1.11 Preservatives must be:

97%

117 rated

Answer

  • Non-poisonous enough to kill insects without being harmful to humans.
  • Be affordable.
  • Not smell unpleasant.
  • Not cause corrosion of the metals.
  • Strengthen the area rather than weaken the wood.
  • Not change the dimensions or the strength of the wood.