FIGURE 1.1 below is an illustration of a worker on a building site - NSC Civil Technology Civil Services - Question 1 - 2017 - Paper 1
Question 1
FIGURE 1.1 below is an illustration of a worker on a building site. Describe TWO safety precautions that the worker should follow to prevent what is happening in the... show full transcript
Worked Solution & Example Answer:FIGURE 1.1 below is an illustration of a worker on a building site - NSC Civil Technology Civil Services - Question 1 - 2017 - Paper 1
Step 1
Describe TWO safety precautions that the worker should follow to prevent what is happening in the illustration.
96%
114 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
Ensure that the worker wears appropriate personal protective equipment (PPE), including a hard hat and safety footwear, to protect against falling objects and slips.
The worker should make sure that the scaffolding is stable, secured properly, and free of any hazards such as liquids or debris to avoid accidents.
Step 2
Explain why electric cables and the wires of power tools must be checked regularly.
99%
104 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
Electric cables and power tool wires must be checked regularly to avoid electric shock hazards. Damaged wires can expose live electricity, leading to potential electrocution or fire risks.
Step 3
Give ONE reason why it is NOT safe to adjust a machine while the blade is in motion (turning).
96%
101 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
It is not safe to adjust a machine while the blade is in motion because the worker can be injured by the moving blade, leading to serious injuries.
Step 4
Name THREE accessories (equipment) that you need to conduct a slump test.
98%
120 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
Tamping rod
Cone
Base plate or waterproof base
Step 5
Recommend ONE method of mixing concrete for bigger projects.
97%
117 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
For larger projects, using a concrete mixer or machine mixed concrete is recommended as it ensures a uniform mixture and saves time.
Step 6
Choose a description from COLUMN B that matches an item in COLUMN A. Write only the letter (A–M) next to the question number (1.6.1–1.6.10) in the ANSWER BOOK.
97%
121 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
1.6.1 E
1.6.2 A
1.6.3 B
1.6.4 D
1.6.5 F
1.6.6 G
1.6.7 K
1.6.8 I
1.6.9 H
1.6.10 J
Step 7
Describe ONE type of equipment that can be used to apply paint to a ceiling.
96%
114 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
A roller can be used to apply paint to a ceiling effectively, ensuring an even application.
Step 8
Give ONE reason for your answer to QUESTION 1.9.1.
99%
104 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
Using a roller is beneficial as it covers larger areas quickly and minimizes the chance of paint dripping or splattering.
Step 9
Name the components (materials) used to close the gap/opening between the following: 1.10.1 Floor covering and the wall.
96%
101 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
Skirting or tile skirting is commonly used to close the gap between the floor covering and the wall.
Step 10
Name the components (materials) used to close the gap/opening between the following: 1.10.2 Wall and the ceiling of a building.
98%
120 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
Cornice is used to close the gap between the wall and the ceiling.