Question 2

Identify-FIGURE-A-NSC Civil Technology Civil Services-Question 2-2018-Paper 1.png

Identify FIGURE A. Identify FIGURE B. Identify number 4. Identify number 5. Identify number 6. Identify number 11. On what date was the plan printed? Who drew the bu... show full transcript

Worked Solution & Example Answer:Identify FIGURE A - NSC Civil Technology Civil Services - Question 2 - 2018 - Paper 1

Step 1

Identify FIGURE A.

96%

114 rated

Answer

The identification for FIGURE A is 'South Elevation/Elevation'.

Step 2

Identify FIGURE B.

99%

104 rated

Answer

The identification for FIGURE B is 'Ground floor plan/Floorplan'.

Step 3

Identify number 4.

96%

101 rated

Answer

Number 4 is identified as 'Suspended floor/Floor level/Dash line/ FFL/Expansion joint'.

Step 4

Identify number 5.

98%

120 rated

Answer

Number 5 is the 'Window Sill'.

Step 5

Identify number 6.

97%

117 rated

Answer

Number 6 is the 'Hand wash basin/Wash basin/Washing basin/HWB/Basin'.

Step 6

Identify number 11.

97%

121 rated

Answer

Number 11 is the 'Water closet/WC/Toilet pan'.

Step 7

On what date was the plan printed?

96%

114 rated

Answer

The plan was printed on '2018/10/02'.

Step 8

Who drew the building plan?

99%

104 rated

Answer

The building plan was drawn by 'JP Maloi'.

Step 9

Name the feature in the column for the notes in FIGURE 2 that must be installed in front of the sliding door.

96%

101 rated

Answer

The feature is a 'Ramp'.

Step 10

Identify the type of roof that is used for the building in FIGURE A.

98%

120 rated

Answer

The type of roof used is a 'Gable roof'.

Step 11

Explain the purpose of number 1.

97%

117 rated

Answer

The purpose of number 1 is to cover the opening/close the gap between the two slopes of the roof and to prevent water and other elements from entering the roof.

Step 12

Explain the purpose of number 2.

97%

121 rated

Answer

The purpose of number 2 is to prevent water from falling onto the ground and to collect rainwater, channeling it into the downpipe and protecting the wall from water.

Step 13

Explain the abbreviation FFL at number 6.

96%

114 rated

Answer

FFL stands for 'Finished floor level'.

Step 14

Explain the purpose of number 7.

99%

104 rated

Answer

The purpose of number 7 is to channel the water from the gutter to the ground.

Step 15

Explain the meaning of the arrow on the feature that must be installed in front of the sliding door.

96%

101 rated

Answer

The arrow indicates the direction of the slope of the ramp; it also indicates the slope's aspect indicating that it rises one meter vertically for every meter horizontally.

Step 16

What room will feature 15 serve?

98%

120 rated

Answer

Feature 15 will serve the 'bathroom'.

Step 17

Explain the short dash lines on the windows.

97%

117 rated

Answer

The short dash lines indicate which direction the window is opening/window opening, as well as the location of the hinges and the location of the casement stay.

Step 18

Deduce the height of window 2 from the window schedule.

97%

121 rated

Answer

The height of window 2 is 1.2 m or 1200 mm (ignore units).

Step 19

Deduce the width of window 3 from the window schedule.

96%

114 rated

Answer

The width of window 3 is 2 m or 2000 mm (ignore units).

Step 20

On what elevation of the building is the bathroom window situated?

99%

104 rated

Answer

The bathroom window is situated on the 'Western elevation/Western side' of the building.