QUESTION 3: CONSTRUCTION ASSOCIATED WITH CIVIL SERVICES, OHSA AND QUANTITIES (SPECIFIC)
FIGURE 3.1 below shows safety equipment - NSC Civil Technology Civil Services - Question 3 - 2023 - Paper 1
Question 3
QUESTION 3: CONSTRUCTION ASSOCIATED WITH CIVIL SERVICES, OHSA AND QUANTITIES (SPECIFIC)
FIGURE 3.1 below shows safety equipment.
3.1.1 Identify A and B.
3.1.2 To ... show full transcript
Worked Solution & Example Answer:QUESTION 3: CONSTRUCTION ASSOCIATED WITH CIVIL SERVICES, OHSA AND QUANTITIES (SPECIFIC)
FIGURE 3.1 below shows safety equipment - NSC Civil Technology Civil Services - Question 3 - 2023 - Paper 1
Step 1
3.1.1 Identify A and B.
96%
114 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
A is the safety harness, and B is the locking snap hook or clip.
Step 2
3.1.2 To what should B be attached?
99%
104 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
B should be attached to a secure anchor point.
Step 3
3.1.3 Name ONE safety item that a worker must wear in order to prevent infections when working with raw sewage.
96%
101 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
One safety item is safety goggles.
Step 4
3.2.1 Identify A to C.
98%
120 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
A is the benching, B is the branch channel, and C is the inlet or inlet pipe.
Step 5
3.2.2 Explain TWO faults that are illustrated in the installation of this manhole.
97%
117 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
The two faults are: 1. The walls are not double-skinned. 2. The concrete bricks are not bonded properly.
Step 6
3.2.3 Name a type of manhole that is NOT built with bricks.
97%
121 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
A concrete ring manhole.
Step 7
3.2.4 A manhole cover is removed for maintenance. Describe ONE safety precaution that needs to be applied to ensure the safety of pedestrians.
96%
114 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
One safety precaution is to cordon off the area and post warning signs.
Step 8
3.3 Calculate the fall of pipe A.
99%
104 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
The fall of pipe A can be calculated using the formula:
ext{Fall} = rac{ ext{Length}}{ ext{Gradient}}
Given the total length is 2 m and the gradient is 1:40:
ext{Fall} = rac{2000}{40} = 50 ext{ mm}
Step 9
3.4 Describe the term backfilling.
96%
101 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
Backfilling is the process of putting soil back into a trench or excavation after installation of utilities or structures.
Step 10
3.5 Use the information in FIGURE 3.5 and take off the quantities of materials.
98%
120 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!