5.1 Name the type of lagging that you would use for the centres when you have to build the following: 5.1.1 Rough arch 5.1.2 Gauged arch 5.2 Draw in your ANSWER BOOK, in good proportion, a centre for a semicircular arch that will be built over a door opening - NSC Civil Technology Woodworking - Question 5 - 2019 - Paper 1

Question icon

Question 5

5.1-Name-the-type-of-lagging-that-you-would-use-for-the-centres-when-you-have-to-build-the-following:--5.1.1-Rough-arch--5.1.2-Gauged-arch--5.2-Draw-in-your-ANSWER-BOOK,-in-good-proportion,-a-centre-for-a-semicircular-arch-that-will-be-built-over-a-door-opening-NSC Civil Technology Woodworking-Question 5-2019-Paper 1.png

5.1 Name the type of lagging that you would use for the centres when you have to build the following: 5.1.1 Rough arch 5.1.2 Gauged arch 5.2 Draw in your ANSWER B... show full transcript

Worked Solution & Example Answer:5.1 Name the type of lagging that you would use for the centres when you have to build the following: 5.1.1 Rough arch 5.1.2 Gauged arch 5.2 Draw in your ANSWER BOOK, in good proportion, a centre for a semicircular arch that will be built over a door opening - NSC Civil Technology Woodworking - Question 5 - 2019 - Paper 1

Step 1

5.1.1 Rough arch

96%

114 rated

Answer

The type of lagging suitable for a rough arch is open lagging. This type allows for a greater adjustment during the setting of the arch.

Step 2

5.1.2 Gauged arch

99%

104 rated

Answer

For a gauged arch, closed lagging is preferable. This provides a more precise mold that supports the arch's defined curvature.

Step 3

5.2 Draw in your ANSWER BOOK, in good proportion, a centre for a semicircular arch that will be built over a door opening. Label any TWO parts on the drawing.

96%

101 rated

Answer

To draw a centre for a semicircular arch, depict a semicircle above a rectangle representing the door. Label the 'RIB' of the arch and the 'TIE BEAM' connecting the ends.

Step 4

5.3 Name the material that can be used for the sides of the formwork for a square column, which saves time because no surface finishing is needed and no absorption of moisture from the concrete takes place.

98%

120 rated

Answer

The material suitable for the sides of the formwork is steel. It provides a smooth finish and prevents moisture absorption, reducing the need for additional surface treatment.

Step 5

5.4 What will you apply to the formwork before the casting of concrete to prevent the concrete from clinging to the inside of the formwork when striking takes place?

97%

117 rated

Answer

Before casting, releasing oil will be applied to the formwork. This creates a lubricated surface, ensuring easy removal of the formwork after the concrete has set.

Step 6

5.5 Use ANSWER SHEET 5.5 and draw, in good proportion, ONLY the left half of the vertical section of the formwork for the concrete beam.

97%

121 rated

Answer

On ANSWER SHEET 5.5, represent the vertical section of the formwork. Include elements such as the 'SHUTTERING BOARD SIDE', 'CLEAT', and 'WEDGE', ensuring correct proportions and clear labeling.

Step 7

5.6 Label A to F.

96%

114 rated

Answer

In FIGURE 5.6, label the components as follows:

  • A: Needle/Cleat
  • B: Straining sill
  • C: Inclined strut/Raking strut
  • D: Horizontal shore/Shore
  • E: Folding wedge
  • F: Wall