Photo AI

Andrew and Duncan went fishing for carp on a friend's farm - NSC Mathematical Literacy - Question 3 - 2023 - Paper 2

Question icon

Question 3

Andrew-and-Duncan-went-fishing-for-carp-on-a-friend's-farm-NSC Mathematical Literacy-Question 3-2023-Paper 2.png

Andrew and Duncan went fishing for carp on a friend's farm. NOTE: Carp is a large freshwater fish that can be eaten by humans. 3.1.1 A female carp can lay 2,7 mill... show full transcript

Worked Solution & Example Answer:Andrew and Duncan went fishing for carp on a friend's farm - NSC Mathematical Literacy - Question 3 - 2023 - Paper 2

Step 1

A female carp can lay 2,7 million eggs. Write 2,7 million in full, using numerals only.

96%

114 rated

Answer

The number of eggs is: 2,700,000.

Step 2

Andrew caught a carp with a mass of 2,375 kg. Duncan caught two carp, one weighing 1,2 kg and the other 750 g. Determine, in kg, the total mass of the carp they caught.

99%

104 rated

Answer

The total mass of all the carp caught is calculated as follows:

  • Andrew's carp: 2.375 kg
  • Duncan's first carp: 1.2 kg
  • Duncan's second carp: 0.750 kg (750 g is converted to kg)

Total mass = 2.375 + 1.2 + 0.750 = 4.325 kg.

Step 3

Calculate, in m³, the total capacity of all the holes dug for the required posts.

96%

101 rated

Answer

The volume of one hole can be calculated using:

Volume = length × width × depth.

Each hole has a side length of 0.3 m and a depth of 0.6 m, so:

Volume of one hole = 0.3 m × 0.3 m × 0.6 m = 0.054 m³.

Total capacity for 12 holes = 12 × 0.054 m³ = 0.648 m³.

Step 4

Give an explanation why he had some concrete left over after planting all the posts in the holes with concrete.

98%

120 rated

Answer

Andrew had leftover concrete because the volume of concrete he mixed was based on the calculation for the holes, and it is likely that when he filled the holes, there was some concrete that was not used, resulting in excess due to factors like spillage, shape of the holes, or slight overestimations in the volume.

Step 5

Calculate the mass of river sand needed to make 1 m³ of concrete.

97%

117 rated

Answer

Using the ratio of ingredients:

If 0.75 m³ of concrete requires 5.5 bags (which is equivalent to the mass of cement), then:

For 1 m³, the mass of cement would be:

Mass of cement for 1 m³ = (5.5 bags / 0.75 m³) × 1 m³ = 7.33 bags.

Given that one level wheelbarrow full of river sand weighs 102 kg, calculate the total sand needed from the ratio:

If the mixture ratio is cement: river sand: stone, calculate the corresponding river sand mass needed for 1 m³.

Step 6

Calculate, in cm², the total area of all the post sides that have to be painted.

97%

121 rated

Answer

Each post cap has a base side of 15.24 cm and a height of 2.5 cm. First, calculate the post cap area:

Area of two sides (each side is 125 mm wide):

Area = 2 × (length × width) = 2 × (160 cm × 0.125 cm) = 40 cm².

For areas of post caps convert to cm² and total accordingly for all required painted faces.

Step 7

Verify, showing all calculations, whether Duncan's statement is VALID.

96%

114 rated

Answer

Calculate total area (posts + caps) based on the previous findings to check if it tallies with the 52 704 cm² mentioned. Show calculations clearly for validation based on summed areas.

Step 8

Calculate how many litres of paint is needed to paint 52 704 cm².

99%

104 rated

Answer

Using the spread rate of paint:

Total area = 52,704 cm² = 5.2704 m².

Required litres = Total area × spread rate = 5.2704 m² × 12.46 litres/m² = Amount needed.

Join the NSC students using SimpleStudy...

97% of Students

Report Improved Results

98% of Students

Recommend to friends

100,000+

Students Supported

1 Million+

Questions answered

;