4.1 Define work done - NSC Technical Sciences - Question 4 - 2021 - Paper 1
Question 4
4.1 Define work done.
4.1.2 Calculate the work done by the applied force over the 8 m.
4.2 A construction worker of mass 75 kg is airlifted vertically upwards from... show full transcript
Worked Solution & Example Answer:4.1 Define work done - NSC Technical Sciences - Question 4 - 2021 - Paper 1
Step 1
Define work done.
96%
114 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
Work done is defined as the product of the force applied on an object and the displacement in the direction of the force. Mathematically, it can be expressed as:
W=Fimesdimesextcos(heta)
where:
W is the work done,
F is the force applied,
d is the displacement,
heta is the angle between the force and the direction of displacement.
Step 2
Calculate the work done by the applied force over the 8 m.
99%
104 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
To calculate the work done:
Identify the values: The force F=60extN, the distance d=8extm, and the angle θ=25°.
Apply the formula for work done:
W=Fimesdimesextcos(heta)
3. Perform the calculations:
Thus, the work done by the applied force is approximately 435 J.
Step 3
State the principle of conservation of mechanical energy in words.
96%
101 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
The principle of conservation of mechanical energy states that the total mechanical energy of an isolated system remains constant, provided that no external forces do work on it. This means that the sum of kinetic energy (KE) and gravitational potential energy (PE) in the system does not change.
Step 4
Calculate the potential energy gained by the construction worker 12 metres above the first floor.
98%
120 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
To calculate the potential energy gained:
Identify the values: The mass m=75extkg and the height h=12extm. The gravitational acceleration g=9.8extm/s2.
Use the formula for potential energy:
PE=mgh
3. Perform the calculations:
PE=75imes9.8imes12PE=8820extJ
The potential energy gained by the construction worker is 8820 J.
Step 5
Calculate his kinetic energy as he is lifted for 12 m.
97%
117 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
To calculate the kinetic energy:
Using the formula for kinetic energy:
KE = rac{1}{2} mv^2
2. Identify the values: As he is lifted at a constant speed v=3extm/s.
3. Perform the calculations:
Thus, his kinetic energy as he is lifted for 12 m is approximately 337.5 J.
Step 6
Determine the potential energy of the construction worker just before he was airlifted by the helicopter.
97%
121 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
To find the potential energy just before he was airlifted, we know the total mechanical energy at the highest point is 11,500 J, which is the sum of potential energy (PE) at that height and kinetic energy (KE) at that height.
Using the relationship:
MEtotal=PE+KE
2. Substituting the values:
11500=PE+337.5
3. Solving for potential energy:
PE=11500−337.5=11162.5extJ
The potential energy of the construction worker just before he was airlifted is approximately 11162.5 J.