10 cards from this deck
Earliest time activity can start after prior activities complete
Latest time activity can start without delaying project
Earliest starting times (EST)
Latest starting times (LST)
EST=0\text{EST} = 0EST=0
Largest EST value
Smallest LST value
EST of predecessor+duration of predecessor\text{EST of predecessor} + \text{duration of predecessor}EST of predecessor+duration of predecessor
LST of successor−duration of activity\text{LST of successor} - \text{duration of activity}LST of successor−duration of activity
Minimum completion time for entire project