What is float time in a project network?
What is float time in a project network?
Time an activity can delay without delays
How is float time calculated?
How is float time calculated?
What is a critical activity?
What is a critical activity?
An activity with zero float time
What does the critical path represent?
What does the critical path represent?
Sequence of critical activities
If Activity has and , what is its float time?
If Activity has and , what is its float time?
units
When an activity has multiple predecessors, which EST value should be used?
When an activity has multiple predecessors, which EST value should be used?
The largest EST value
When an activity has multiple successors, which LST value should be used?
When an activity has multiple successors, which LST value should be used?
The smallest LST value
Where is the minimum project completion time found?
Where is the minimum project completion time found?
EST value at the finish
What happens if a critical activity is delayed?
What happens if a critical activity is delayed?
The entire project is delayed
Which activities are on the critical path?
Which activities are on the critical path?
Activities with zero float time