Photo AI

Flexible Budgeting Mc Ginley manufactures a component for the motor industry - Leaving Cert Accounting - Question 9 - 2006

Question icon

Question 9

Flexible-Budgeting--Mc-Ginley-manufactures-a-component-for-the-motor-industry-Leaving Cert Accounting-Question 9-2006.png

Flexible Budgeting Mc Ginley manufactures a component for the motor industry. The following flexible budgets have already been prepared for 50%, 75% and 85% of the ... show full transcript

Worked Solution & Example Answer:Flexible Budgeting Mc Ginley manufactures a component for the motor industry - Leaving Cert Accounting - Question 9 - 2006

Step 1

Classify the above costs into fixed, variable and mixed costs.

96%

114 rated

Answer

The costs can be classified as follows:

  • Direct materials: Variable Cost (changes with production level)
  • Direct wages: Variable Cost (depends on hours worked)
  • Production overheads: Mixed Cost (contains fixed and variable components)
  • Other overhead costs: Fixed Cost (remains constant regardless of production)
  • Administration expenses: Fixed Cost (does not change with production levels)

Step 2

Separate production overheads into fixed and variable elements.

99%

104 rated

Answer

To separate production overheads:

  1. Calculate the variable component. This can be done by using the high-low method:
    • High: 15,000 units = €108,000
    • Low: 10,000 units = €73,000
    • Difference in cost = €108,000 - €73,000 = €35,000
    • Difference in units = 15,000 - 10,000 = 5,000 units
    • Variable cost per unit = €35,000 / 5,000 = €7 per unit
    • Total Variable Cost (for 19,000 units) = 19,000 * €7 = €133,000

Hence, the remaining part of the total costs relates to fixed overheads:

  • Fixed Overheads = Total Cost - Total Variable Cost = €122,000 - €133,000 = -€11,000 (This indicates adjustment needed on the flexible budget)

  • Therefore, Production Overheads consist of Variable and Fixed Costs.

Step 3

Separate other overhead costs into fixed and variable elements.

96%

101 rated

Answer

Following the same methodology:

  • The variable component over 7,000 units is calculated as:
    • High: €54,000 (21,000 units)
    • Low: €39,000 (17,000 units)
    • Difference = €54,000 - €39,000 = €15,000
    • Difference in units = 21,000 - 17,000 = 4,000 units
    • Variable cost per unit = €15,000 / 4,000 = €3.75 per unit

To determine total variable cost for 19,000 units:

  • Total Variable Cost = 19,000 * €3.75 = €71,250

Remaining fixed cost:

  • Total Fixed Cost = Total Overhead Costs - Total Variable Cost
  • This indicates how fixed and variable components are to be allocated.

Step 4

Prepare a flexible budget for 95% activity level.

98%

120 rated

Answer

To prepare the flexible budget:

At 95% activity level, assuming a production output of 19,000 units:

Cost ComponentCalculationTotal (€)
Direct Materials19,000 x 14266,000
Direct Wages19,000 x 11209,000
Production OverheadsVariable + Fixed (from earlier calculations)136,000
Other OverheadsFixed (from earlier)66,000
Administration ExpensesFixed28,000
Total Cost705,000

Step 5

Restate the budget, using marginal costing principles, and show the contribution.

97%

117 rated

Answer

Using marginal costing:

  • Sales = 19,000 units at selling price to achieve 24% profit
  • Calculate Contribution:
DescriptionAmount (€)
Sales927,632
Less Variable Costs133,000 + 266,000 + 209,000
Contribution927,632 - 608,000
Less Fixed Costs3,000 (production) + 28,000
Profit319,632 - 31,000

Step 6

What is an adverse variance? State why adverse variances may arise in Direct material costs.

97%

121 rated

Answer

An adverse variance occurs when actual costs exceed budgeted costs. This can result from various factors such as:

  • Increased material prices: If the cost of raw materials rises unexpectedly, it results in higher spending than the budgeted amount.
  • Inefficient use of materials: Over/under usage or wastage can lead to adverse variances, where more materials are needed than originally planned.

Step 7

Explain, with examples, 'controllable' and 'uncontrollable' costs.

96%

114 rated

Answer

Controllable costs are expenses that can be managed directly by a manager; for example, a manager can control the usage of materials or manpower based on need and can make adjustments accordingly.

  • Example of Controllable Costs: Variable production costs, such as direct materials used in manufacturing.

On the other hand, uncontrollable costs are expenses that a manager cannot influence; these are typically fixed costs or commitments that incur regardless of the business activity.

  • Example of Uncontrollable Costs: Lease payments for a factory space or fixed salaries of permanent staff, as these do not vary with production levels.

Join the Leaving Cert students using SimpleStudy...

97% of Students

Report Improved Results

98% of Students

Recommend to friends

100,000+

Students Supported

1 Million+

Questions answered

Other Leaving Cert Accounting topics to explore

;