Absorption Costing: Tember Ltd., a small jobbing company, has the following budgeted costs for the coming year: € Direct materials 158,000 Direct labour 56,000 Factory overheads 84,000 For the coming year the company has also budgeted 7,000 labour hours and 12,000 machine hours - Leaving Cert Accounting - Question 8 - 2005

Question icon

Question 8

Absorption-Costing:--Tember-Ltd.,-a-small-jobbing-company,-has-the-following-budgeted-costs-for-the-coming-year:--€-Direct-materials-158,000-Direct-labour-56,000-Factory-overheads-84,000--For-the-coming-year-the-company-has-also-budgeted-7,000-labour-hours-and-12,000-machine-hours-Leaving Cert Accounting-Question 8-2005.png

Absorption Costing: Tember Ltd., a small jobbing company, has the following budgeted costs for the coming year: € Direct materials 158,000 Direct labour 56,000 Fac... show full transcript

Worked Solution & Example Answer:Absorption Costing: Tember Ltd., a small jobbing company, has the following budgeted costs for the coming year: € Direct materials 158,000 Direct labour 56,000 Factory overheads 84,000 For the coming year the company has also budgeted 7,000 labour hours and 12,000 machine hours - Leaving Cert Accounting - Question 8 - 2005

Step 1

The overhead absorption rate per machine hour.

96%

114 rated

Answer

To calculate the overhead absorption rate per machine hour, use the formula:

extOverheadAbsorptionRateperMachineHour=Total Factory OverheadsTotal Machine Hours ext{Overhead Absorption Rate per Machine Hour} = \frac{\text{Total Factory Overheads}}{\text{Total Machine Hours}}

Substituting the values:

=84,00012,000=7= \frac{84,000}{12,000} = €7

Step 2

The overhead absorption rate per direct labour hour.

99%

104 rated

Answer

To find the overhead absorption rate per direct labour hour, employ the formula:

Overhead Absorption Rate per Labour Hour=Total Factory OverheadsTotal Labour Hours\text{Overhead Absorption Rate per Labour Hour} = \frac{\text{Total Factory Overheads}}{\text{Total Labour Hours}}

Using the given data:

=84,0007,000=12= \frac{84,000}{7,000} = €12

Step 3

The cost of job number 624 using the overhead absorption rate per machine hour.

96%

101 rated

Answer

To calculate the cost of job number 624 using the overhead absorption rate per machine hour, compute:

  1. Direct Materials: €10,000

  2. Direct Labour: For 250 machine hours:

    250 hours×7=1,750250 \text{ hours} \times €7 = €1,750
  3. Total Cost:

    =10,000+1,750=11,750= 10,000 + 1,750 = €11,750

Step 4

The cost of job number 624 using the overhead absorption rate per direct labour hour.

98%

120 rated

Answer

Using the direct labour overhead absorption rate to determine the cost of job number 624:

  1. Direct Materials: €10,000

  2. Direct Labour: For 170 direct labour hours:

    170 hours×12=2,040170 \text{ hours} \times €12 = €2,040
  3. Total Cost:

    =10,000+2,040=12,040= 10,000 + 2,040 = €12,040

Step 5

The selling prices of job number 624 to the customer using both overhead absorption rates.

97%

117 rated

Answer

To determine the selling price of job number 624 with a 25% mark-up, first calculate:

  1. Cost using machine hours absorption: €11,750

    SellingPrice=11,750×(1+0.25)=14,687.50Selling Price = 11,750 \times (1 + 0.25) = 14,687.50
  2. Cost using labour hours absorption: €12,040

    SellingPrice=12,040×(1+0.25)=15,050Selling Price = 12,040 \times (1 + 0.25) = 15,050

Join the Leaving Cert students using SimpleStudy...

97% of Students

Report Improved Results

98% of Students

Recommend to friends

100,000+

Students Supported

1 Million+

Questions answered

;