Question 1
The main entrance to a dwelling house, as shown in the accompanying sketch, provides access for a person in a wheelchair. The door opening is located in a 300mm exte... show full transcript
Step 1
Answer
To create the vertical section:
Foundation: Begin with the foundation, showing a depth of 300mm, which should be reinforced with mild steel bars. Include a damp-proof course (DPC) positioned behind the concrete cill.
Threshold Detail: The threshold should feature a proprietary threshold unit which ensures water drainage. This unit should be detailed with a slope of 1:15 to facilitate rainwater removal.
Ground Floor: Draw the 20mm quarry tile finish above the threshold, indicating the continuation of the block wall up to the finished floor level.
Door Detail: Illustrate the solid wooden door positioned accurately. Ensure to note the cavity spacing and insulation details within the external wall.
Scale: Ensure all details are properly scaled to a 1:5 ratio on the drawing for clarity.
Step 2
Answer
For rainwater management:
Slope Design: Ensure that the configuration of the threshold incorporates a slope away from the door, directing rainwater towards a drainage channel. This should be specified as a proprietary drainage channel.
Drainage Channel: Integrate a drainage channel at the bottom of the threshold that discharges rainwater to a suitable location, preventing water from pooling.
Material Selection: Use materials that can withstand moisture and prevent water ingress into the inner surfaces, including a DPC, solid block construction, and waterproof finishes where applicable.
Construction Details: Clearly depict these details on the section to demonstrate how water is managed effectively around the entrance.