One corner of a trench for a strip foundation is shown in the sketch - Leaving Cert Construction Studies - Question 4 - 2013
Question 4
One corner of a trench for a strip foundation is shown in the sketch. Describe, using notes and neat freehand sketches, the setting-out of a typical strip foundation... show full transcript
Worked Solution & Example Answer:One corner of a trench for a strip foundation is shown in the sketch - Leaving Cert Construction Studies - Question 4 - 2013
Step 1
levelling the profiles
96%
114 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
To level the profiles for setting out the foundation:
Setting Out: Begin by establishing a datum point that is usually taken from a defined reference height.
Using Levels: Employ spirit levels or laser levels to ensure that the profiles are vertical and horizontal at all points.
Water Levels: Where sustainability is needed, a water level can also be used, ensuring a precise transfer of height.
Adjustments: Make necessary adjustments based on the finished floor level to maintain accuracy.
Step 2
locating the position of the trench
99%
104 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
To locate the trench's position:
Identify Corners: Mark the corners of the building using string lines stretched between the markers in the ground.
External Wall Layout: Confirm the external wall's outline with measurements taken from the identified corners.
Width Marking: Clearly indicate the trench width on profile boards to guide excavation.
Step 3
squaring the corner of the trench
96%
101 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
To square the corner of the trench:
Define the Rectangle: The first step is to outline a rectangle based on the building's layout and location.
Right Angles: Use a 3-4-5 triangle method to ensure accurate right angles at the corners.
Check Alignment: Verify the notation against the drawn rectangle to make sure it corresponds properly.
Step 4
locating the finished level of the concrete in the foundation
98%
120 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
To locate the finished level of the concrete:
Driving Pegs: Place pegs at the required height in line with the finished level of the concrete.
Top of the Trench: Ensure these pegs are level with the top surface of the proposed foundation.
Using Laser Levels: Employ laser levels for consistent accuracy in measuring the concrete's required height above the physical trench.
Step 5
Sketch of a typical strip foundation
97%
117 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
In the sketch, depict a strip foundation for a 350 mm concrete block wall:
Foundation Dimensions: Clearly illustrate the foundation base, with a width of at least 350 mm.
Reinforcement Bar Positioning: Indicate the location of reinforcing bars within the foundation.
Three Dimensions: Include and label at least three typical dimensions, such as the width, depth, and spacing of reinforcement.