A house built to nZEB standards has a highly insulated solid concrete ground floor with a hardwood finish, as shown - Leaving Cert Construction Studies - Question 5 - 2020
Question 5
A house built to nZEB standards has a highly insulated solid concrete ground floor with a hardwood finish, as shown.
(a) Calculate the U-value of the floor, given t... show full transcript
Worked Solution & Example Answer:A house built to nZEB standards has a highly insulated solid concrete ground floor with a hardwood finish, as shown - Leaving Cert Construction Studies - Question 5 - 2020
Step 1
Calculate the U-value of the floor
96%
114 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
To determine the U-value, we need to calculate the total resistance (R) of all the components and then apply the formula:
U=Rtotal1
Finally, calculate U-value: U=Rtotal1=9.9931=0.100m2/W°C
Hence, the U-value of the floor is 0.10 m²/W°C.
Step 2
Using the U-value of the floor obtained at 5(a), calculate the cost of heat lost annually through the floor
99%
104 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
We use the formula for heat loss:
Heat lost=U×Area×(Tinternal−Texternal)(W)
Where:
Area of floor slab = 6.5 m x 9.0 m = 58.5 m².
Temperature difference = 20°C - 6°C = 14°C.
Calculate heat loss per hour:
Q=0.10×58.5×14=81.9 Watts.
Calculating for yearly heat loss:
Heating period = 39 weeks. Days = 7, Hours in a day = 24
Total hours = 39 weeks x 7 days/week x 24 hours/day = 6552 hours.
Total Heat loss = 81.9 Watts x 6552 hours = 536,653.8
Cost of energy:
extCost=1000536,653.8×0.96=€18.62.
Step 3
Using notes and a freehand sketch, show best practice detailing that will prevent the formation of a thermal bridge
96%
101 rated
Only available for registered users.
Sign up now to view full answer, or log in if you already have an account!
Answer
To prevent thermal bridging at the junction of the concrete floor and external wall, consider the following best practices:
Use an insulation layer that extends underneath the wall to eliminate direct contact between the cold wall and the warm concrete.
Ensure that there is a continuous layer of insulation without gaps or thermal breaks.
Incorporate a damp proof membrane to protect the insulation from moisture ingress.
Additional measures may include using insulated foundation blocks and ensuring that thermal insulation wraps around the slab edge.
The sketch should visually demonstrate the layers of insulation, the positioning of the damp proof membrane, and any necessary junction details to achieve the recommended best practices.
Join the Leaving Cert students using SimpleStudy...