A triple-glazed wooden casement window, as shown, is fixed in a 400 mm external concrete block wall with a full-fill insulated cavity - Leaving Cert Construction Studies - Question 5 - 2017

Question icon

Question 5

A-triple-glazed-wooden-casement-window,-as-shown,-is-fixed-in-a-400-mm-external-concrete-block-wall-with-a-full-fill-insulated-cavity-Leaving Cert Construction Studies-Question 5-2017.png

A triple-glazed wooden casement window, as shown, is fixed in a 400 mm external concrete block wall with a full-fill insulated cavity. The fixed frame of the window ... show full transcript

Worked Solution & Example Answer:A triple-glazed wooden casement window, as shown, is fixed in a 400 mm external concrete block wall with a full-fill insulated cavity - Leaving Cert Construction Studies - Question 5 - 2017

Step 1

To a scale of 1.5, draw a vertical section through the external wall and bottom portion of the window, showing the fixed frame of the window and the concrete cill.

96%

114 rated

Answer

  1. Start by sketching the concrete block wall, measuring 400 mm thick, and ensure to indicate the filled insulation cavity.
  2. Draw the external leaf and the internal plaster with dimensions. The fixed frame of the window should measure 100 mm in width and 80 mm in height.
  3. Illustrate the typical details including a 19 mm external render, wall ties, and insulation:
    • Use a proprietary cavity closer at the top of the frame.
    • Include a 200 mm full-fill cavity insulation within the wall.
    • Show a damp-proof course (dpc) to prevent moisture ingress, wrapped around the window frame.
  4. Dimension the drawing and highlight the critical details as requested, ensuring you emphasize three typical dimensions, like the back of the concrete cill to the sill.
  5. Ensure that the framing of the triple glazing is accurately depicted, with the glass noted accordingly, and includes a 25 mm width of the window board.

Step 2

Show on your drawing the typical design detailing to prevent the formation of a thermal/cold bridge at the concrete cill.

99%

104 rated

Answer

  1. Indicate the insulation placed at the back of the concrete cill to prevent thermal bridging.
  2. Draw the damp-proof course (dpc) wrapped around the concrete cill clearly to show its role in moisture prevention.
  3. Include an expanded metal mesh to prevent shrinkage cracks between the insulation and concrete blocks, ensuring structural integrity.
  4. Ensure that the triple-glazed frame encapsulates these details, demonstrating an understanding of building regulations for insulation and moisture control.

Join the Leaving Cert students using SimpleStudy...

97% of Students

Report Improved Results

98% of Students

Recommend to friends

100,000+

Students Supported

1 Million+

Questions answered

;