Critical Path Analysis (Edexcel A-Level Business): Quizzes

📚Quizzes
Critical Path Analysis
Sign up to keep practising.Create a free account to play more quizzes and track your progress.

Practise the questions

10 questions from this quiz

Show

What does CPA calculate for a project?

Minimum time to complete

How does CPA help with working capital?

Enables JIT material purchasing

What do arrows represent in network diagrams?

Tasks or activities

When paths converge at a node during EST calculation, which time is used?

The longest time

Which direction do you work when calculating LFT?

Backwards from end

What TWO conditions identify the critical path?

EST = LFT & longest route

What is the formula for total float?

LFT - EST - Duration

What total float do critical path tasks have?

Zero float

In complex networks with parallel tasks, what time counts toward the total?

Only the longest task

Which phrase describes a key CPA limitation?

Garbage in, garbage out