Gantt (Cascade) Charts (Edexcel A-Level Further Mathematics): Flashcards

📚Flashcards
Gantt (Cascade) Charts
Sign up to keep revising.Create a free account to study more flashcards and track your progress.

Practise the cards

10 cards from this deck

Show

Purpose of Gantt charts

Visual tool to schedule and manage projects, showing timeline view of activities

Alternative name for Gantt charts

Cascade charts

Definition of total float

Time an activity can be delayed without affecting overall project completion

Formula for total float

TF=L−E−dTF = L - E - d

Meaning of zero total float

Activity is on the critical path

What LL represents in TF=L−E−dTF = L - E - d

Latest Finish Time (LFT)

What EE represents in TF=L−E−dTF = L - E - d

Earliest Start Time (EST)

What dd represents in TF=L−E−dTF = L - E - d

Duration of the activity

Requirement for critical path activities

Must start and finish on time to avoid delaying the project

How float is shown on a Gantt chart

By extending bars

Explore Edexcel A-Level Further Mathematics Revision Notes by Topics

Explore Edexcel A-Level Further Mathematics Model Answers by Topics

Explore Edexcel A-Level Further Mathematics Quizzes by Topics

Explore Edexcel A-Level Further Mathematics Exam Questions by Topics

Join 100,000+ A-Level students studying Flashcards with us.

Select your subjects, and get access to A+ resources today.