10 cards from this deck
Visual tool to schedule and manage projects, showing timeline view of activities
Cascade charts
Time an activity can be delayed without affecting overall project completion
TF=L−E−dTF = L - E - dTF=L−E−d
Activity is on the critical path
Latest Finish Time (LFT)
Earliest Start Time (EST)
Duration of the activity
Must start and finish on time to avoid delaying the project
By extending bars