Complete project using least number of workers
Some tasks must finish before others can start
No flexibility in times; delays affect entire project
Can be rescheduled within their float
Amount of time a non-critical activity can be delayed
Float=LFT−EST−Duration\text{Float} = \text{LFT} - \text{EST} - \text{Duration}Float=LFT−EST−Duration
Max number of overlapping activities at any time
Not using float to reduce worker overlap
Starting dependent activities too early
Delay non-critical activities to reduce overlap