Scheduling Activities (Edexcel A-Level Further Mathematics): Flashcards

📚Flashcards
Scheduling Activities
Sign up to keep revising.Create a free account to study more flashcards and track your progress.

Practise the cards

10 cards from this deck

Show

Main goal of scheduling activities

Complete project using least number of workers

What are precedence constraints?

Some tasks must finish before others can start

Define critical activities

No flexibility in times; delays affect entire project

Define non-critical activities

Can be rescheduled within their float

What is float in scheduling?

Amount of time a non-critical activity can be delayed

Formula for total float

Float=LFT−EST−Duration\text{Float} = \text{LFT} - \text{EST} - \text{Duration}

How to calculate total workers needed?

Max number of overlapping activities at any time

Common mistake: ignoring what?

Not using float to reduce worker overlap

Common mistake with dependencies

Starting dependent activities too early

How to use float to minimise workers?

Delay non-critical activities to reduce overlap

Explore Edexcel A-Level Further Mathematics Revision Notes by Topics

Explore Edexcel A-Level Further Mathematics Model Answers by Topics

Explore Edexcel A-Level Further Mathematics Quizzes by Topics

Explore Edexcel A-Level Further Mathematics Exam Questions by Topics

Join 100,000+ A-Level students studying Flashcards with us.

Select your subjects, and get access to A+ resources today.