Activity Networks & Precedence Tables (Edexcel A-Level Further Mathematics): Quizzes

📚Quizzes
Activity Networks & Precedence Tables
Sign up to keep practising.Create a free account to play more quizzes and track your progress.

Practise the questions

10 questions from this quiz

Show

In an activity network, what do nodes represent?

Events (start/completion of activities)

In an activity network, what do edges represent?

Activities, labelled with duration

What does a precedence table list for each activity?

Immediate predecessors only

Activity DD depends on BB and CC. What are BB and CC called?

Immediate predecessors of DD

What is the first step in constructing an activity network?

Identify nodes & assign start node

How many start nodes and end nodes should an activity network have?

One start, one end

What is a common mistake when using precedence tables?

Adding unnecessary dependencies

What leads to an incomplete activity network graph?

Omitting single start or end node

When can activity XX start according to the dependency rule?

After all immediate predecessors finish

To find predecessors of XX in a precedence table from a network, what do you identify?

Activities ending at start of XX

Explore Edexcel A-Level Further Mathematics Revision Notes by Topics

Explore Edexcel A-Level Further Mathematics Model Answers by Topics

Explore Edexcel A-Level Further Mathematics Flashcards by Topics

Explore Edexcel A-Level Further Mathematics Exam Questions by Topics

Join 100,000+ A-Level students studying Quizzes with us.

Select your subjects, and get access to A+ resources today.