What is the primary purpose of a Gantt chart in project management?
What is the primary purpose of a Gantt chart in project management?
To schedule and manage project tasks
What is the formula for calculating total float (TF)?
What is the formula for calculating total float (TF)?
What does total float represent?
What does total float represent?
Time an activity can be delayed without delay
What does a total float of zero indicate about an activity?
What does a total float of zero indicate about an activity?
It lies on the critical path
Activity has , , . What is the total float?
Activity has , , . What is the total float?
What do horizontal bars represent on a Gantt chart?
What do horizontal bars represent on a Gantt chart?
Activities along a timeline
What happens if a critical path activity is delayed?
What happens if a critical path activity is delayed?
Overall project completion is delayed
What does Latest Finish Time (LFT) represent?
What does Latest Finish Time (LFT) represent?
Latest time to finish without delaying project
What does Earliest Start Time (EST) represent?
What does Earliest Start Time (EST) represent?
Earliest time activity can start
When can an activity start if it has dependencies?
When can an activity start if it has dependencies?
Only after all predecessors complete