What is the main goal when scheduling activities in a project?
What is the main goal when scheduling activities in a project?
Use least number of workers
Which statement describes critical activities?
Which statement describes critical activities?
No flexibility; delays affect project
What is the purpose of float in non-critical activities?
What is the purpose of float in non-critical activities?
Optimize worker usage
What is the formula for total float?
What is the formula for total float?
How is the total number of workers calculated?
How is the total number of workers calculated?
Max overlapping activities anytime
What are precedence constraints in scheduling?
What are precedence constraints in scheduling?
Some tasks must finish before others
Which is a common mistake in scheduling?
Which is a common mistake in scheduling?
Ignoring float values
What happens if critical activity start times are changed?
What happens if critical activity start times are changed?
Project completion delayed
In Example 1, how many workers are required for activities , , , ?
In Example 1, how many workers are required for activities , , , ?
2 workers
In Example 2, what is activity 's float in weeks?
In Example 2, what is activity 's float in weeks?
2 weeks