Critical Path Analysis (Edexcel A-Level Further Mathematics): Flashcards
📚Flashcards
Practise the cards
10 cards from this deck
ShowHide
Practise the cards
10 cards from this deck
What do nodes represent in activity networks?
What do nodes represent in activity networks?
Events (start/completion of activities)
What do edges represent in activity networks?
What do edges represent in activity networks?
Activities with duration labels
What does a precedence table list?
What does a precedence table list?
Activities & immediate predecessors
Immediate predecessors are
Immediate predecessors are
Direct dependencies only
Start nodes in activity network
Start nodes in activity network
Single start node only
End nodes in activity network
End nodes in activity network
Single end node only
When activity can start
When activity can start
After all immediate predecessors complete
Edge direction indicates
Edge direction indicates
Sequence of activities
Common precedence table error
Common precedence table error
Listing all predecessors instead of immediate ones only
Activity network flow
Activity network flow
Single start node to single end node
