Critical Path Analysis (Edexcel A-Level Further Mathematics): Flashcards

📚Flashcards
Critical Path Analysis
Sign up to keep revising.Create a free account to study more flashcards and track your progress.

Practise the cards

10 cards from this deck

Show

Critical path in CPA

Longest path through network; determines minimum project duration

Float of critical path activities

Zero

EET (Earliest Event Time)

Earliest time an event can occur

LET (Latest Event Time)

Latest time event can occur without delay

EFT formula

EFT=EST+Duration\text{EFT} = \text{EST} + \text{Duration}

LST formula

LST=LFTDuration\text{LST} = \text{LFT} - \text{Duration}

Float formula

Float=LFTEFT\text{Float} = \text{LFT} - \text{EFT}

Identifying critical activities

Activities with zero float

Lower bound for workers

Total Activity TimeProject Duration\lceil \frac{\text{Total Activity Time}}{\text{Project Duration}} \rceil

EET calculation in forward pass

max(EFT of preceding activities)\max(\text{EFT of preceding activities})

Explore Edexcel A-Level Further Mathematics Revision Notes by Topics

Explore Edexcel A-Level Further Mathematics Model Answers by Topics

Explore Edexcel A-Level Further Mathematics Quizzes by Topics

Explore Edexcel A-Level Further Mathematics Exam Questions by Topics

Join 100,000+ A-Level students studying Flashcards with us.

Select your subjects, and get access to A+ resources today.