Revision notes with simplified explanations to understand Gantt (Cascade) Charts quickly and effectively.
440+ students studying
Gantt charts (also known as cascade charts) are a visual tool used to schedule and manage projects. They provide a timeline view of activities and highlight when tasks start, their durations, and how they relate to one another.
In A-Level Further Maths, Gantt charts are closely tied to Critical Path Analysis (CPA). We often calculate the total float of an activity and use this to schedule tasks efficiently on a Gantt chart, ensuring each activity requires only one worker at a time.
The total float of an activity is the amount of time that an activity can be delayed without affecting the overall project completion time. It is calculated using:
where:
If the total float is zero, the activity lies on the critical path, meaning it must start and finish on time to avoid delaying the project.
A Gantt chart represents activities as horizontal bars along a timeline. It visually shows:
Step 1: Given Information
Consider the following activities, their durations, and the earliest and latest times:
Activity | Duration (dd) | Earliest Start (EE) | Latest Finish (LL) |
---|---|---|---|
A | 4 | 0 | 6 |
B | 3 | 4 | 9 |
C | 2 | 7 | 9 |
D | 5 | 0 | 10 |
Step 2: Calculate Total Float
Using :
Step 3: Draw the Gantt Chart
Visualizing the Gantt chart:
Time: 0 1 2 3 4 5 6 7 8 9 10
Activity A: ████----
Activity B: ███----
Activity C: ██
Activity D: █████----
Key:
Step 1: Given Information
The project has the following dependencies:
Activity | Duration (dd) | Depends on | Earliest Start (EE) | Latest Finish (LL) |
---|---|---|---|---|
A | 2 | - | 0 | 3 |
B | 3 | A | 2 | 6 |
C | 4 | A | 2 | 6 |
D | 5 | B, C | 6 | 12 |
Step 2: Calculate Total Float
Step 3: Draw the Gantt Chart
Considering the dependencies:
Visualizing the Gantt chart:
Time: 0 1 2 3 4 5 6 7 8 9 10 11 12
Activity A: ██-
Activity B: ███-
Activity C: ████
Activity D: █████
Enhance your understanding with flashcards, quizzes, and exams—designed to help you grasp key concepts, reinforce learning, and master any topic with confidence!
70 flashcards
Flashcards on Gantt (Cascade) Charts
Revise key concepts with interactive flashcards.
Try Further Maths Decision Maths 1 Flashcards7 quizzes
Quizzes on Gantt (Cascade) Charts
Test your knowledge with fun and engaging quizzes.
Try Further Maths Decision Maths 1 Quizzes29 questions
Exam questions on Gantt (Cascade) Charts
Boost your confidence with real exam questions.
Try Further Maths Decision Maths 1 Questions27 exams created
Exam Builder on Gantt (Cascade) Charts
Create custom exams across topics for better practice!
Try Further Maths Decision Maths 1 exam builder50 papers
Past Papers on Gantt (Cascade) Charts
Practice past papers to reinforce exam experience.
Try Further Maths Decision Maths 1 Past PapersDiscover More Revision Notes Related to Gantt (Cascade) Charts to Deepen Your Understanding and Improve Your Mastery
96%
114 rated
Critical Path Analysis
Activity Networks & Precedence Tables
411+ studying
195KViewsJoin 500,000+ A-Level students using SimpleStudy...
Join Thousands of A-Level Students Using SimpleStudy to Learn Smarter, Stay Organized, and Boost Their Grades with Confidence!
Report Improved Results
Recommend to friends
Students Supported
Questions answered