11.1.5 Resource Histograms

Introduction

A resource histogram is a bar chart used to visually represent the number of workers (or resources) required over the duration of a project. This tool helps to assess the workforce demands and ensures that the necessary resources are available at the right times.

In A-Level Further Maths, constructing resource histograms involves:

  1. Allocating workers to specific activities.
  2. Using the project timeline (e.g., derived from a Gantt chart) to determine the number of workers required at each time interval.

Steps to Construct a Resource Histogram

  • Understand the Problem
  • Collect Key Information
  • Build the Histogram

1. Understand the Problem

  • Each activity has a start time, duration, and number of workers required.
  • Use the timeline of activities (e.g., from a Gantt chart) to calculate the total number of workers needed at each time step.

2. Collect Key Information

For each activity, note:

  • Start and finish times.
  • Number of workers required.
  • Duration of the activity.

3. Build the Histogram

  • Divide the timeline into units (e.g., days, weeks).
  • For each unit, sum the workers needed across all activities in progress.
  • Draw a bar for each time interval representing the total workforce.

Worked Example

infoNote

Example 1: Construct a Resource Histogram


Step 1: Given Information

ActivityStart TimeDuration (days)Workers Required
A032
B243
C424
D531

Step 2: Analyse Overlaps

  • Activity A runs from day 0 to day 2.
  • Activity B starts at day 2 and overlaps with Activity A for 1 day.
  • Activity C starts at day 4, overlaps with Activity B for 1 day, and then continues independently.
  • Activity D starts at day 5, overlaps with Activity C for 2 days.

Step 3: Calculate Workers at Each Day

DayWorkers from AWorkers from BWorkers from CWorkers from DTotal Workers
020002
120002
223005
303003
403407
500415
600415
700011

Step 4: Draw the Resource Histogram

The resource histogram can be represented as follows:

Day:       0   1   2   3   4   5   6   7
Workers:   ██  ██  █████  ███  ███████ █████  █████  █


Key:

  • The height of each bar represents the total workers needed for that day.
  • Activities contributing to each total are determined from the table.
infoNote

Example 2: Histogram with Non-Uniform Durations


Step 1: Given Information

ActivityStart TimeDuration (weeks)Workers Required
A025
B134
C326

Step 2: Analyse Overlaps

  • Activity A runs from week 0 to week 1.
  • Activity B starts at week 1, overlaps with Activity A in week 1, and continues until week 3.
  • Activity C starts at week 3, overlaps with Activity B in week 3, and then continues independently.

Step 3: Calculate Workers at Each Week

WeekWorkers from AWorkers from BWorkers from CTotal Workers
05005
15409
20404
304610
40066

Step 4: Draw the Resource Histogram

Week:      0   1   2   3   4
Workers:   █████  █████████ ████ ██████████ ██████


Key:

  • Bars clearly show workforce demand by week.
  • Overlaps of activities result in taller bars.

Note Summary

infoNote

Common Mistakes

  1. Forgetting overlaps: Not summing workers from activities that occur simultaneously.
  2. Incorrect time intervals: Misaligning activities with the timeline.
  3. Misinterpreting durations: Confusing start and finish times with durations.
  4. Omitting zero contributions: Failing to account for periods when no workers are required.
  5. Poor visualization: Drawing inconsistent or unclear bars in the histogram.
infoNote

Key Formulas

  1. Resource calculation: Total workers = sum of workers for overlapping activities.
  2. Start and finish times:
  • Finish time = start time + duration.
  1. Histogram representation:
  • Height of the bar = total workers required at each time step.
  1. Overlaps:
  • Add contributions from all activities running during the same time interval.
Books

Only available for registered users.

Sign up now to view the full note, or log in if you already have an account!

500K+ Students Use These Powerful Tools to Master Resource Histograms

Enhance your understanding with flashcards, quizzes, and exams—designed to help you grasp key concepts, reinforce learning, and master any topic with confidence!

70 flashcards

Flashcards on Resource Histograms

Revise key concepts with interactive flashcards.

Try Further Maths Decision Maths 1 Flashcards

7 quizzes

Quizzes on Resource Histograms

Test your knowledge with fun and engaging quizzes.

Try Further Maths Decision Maths 1 Quizzes

29 questions

Exam questions on Resource Histograms

Boost your confidence with real exam questions.

Try Further Maths Decision Maths 1 Questions

27 exams created

Exam Builder on Resource Histograms

Create custom exams across topics for better practice!

Try Further Maths Decision Maths 1 exam builder

50 papers

Past Papers on Resource Histograms

Practice past papers to reinforce exam experience.

Try Further Maths Decision Maths 1 Past Papers

Other Revision Notes related to Resource Histograms you should explore

Discover More Revision Notes Related to Resource Histograms to Deepen Your Understanding and Improve Your Mastery

96%

114 rated

Critical Path Analysis

Activity Networks & Precedence Tables

user avatar
user avatar
user avatar
user avatar
user avatar

432+ studying

184KViews

96%

114 rated

Critical Path Analysis

Dummy Activities

user avatar
user avatar
user avatar
user avatar
user avatar

289+ studying

188KViews

96%

114 rated

Critical Path Analysis

Critical Path Analysis

user avatar
user avatar
user avatar
user avatar
user avatar

458+ studying

186KViews

96%

114 rated

Critical Path Analysis

Gantt (Cascade) Charts

user avatar
user avatar
user avatar
user avatar
user avatar

267+ studying

192KViews
Load more notes

Join 500,000+ A-Level students using SimpleStudy...

Join Thousands of A-Level Students Using SimpleStudy to Learn Smarter, Stay Organized, and Boost Their Grades with Confidence!

97% of Students

Report Improved Results

98% of Students

Recommend to friends

500,000+

Students Supported

50 Million+

Questions answered