Activity networks and precedence tables are tools used to model and manage projects efficiently. They show the relationships between activities, highlighting dependencies and the order in which tasks must be completed.
An activity network is a directed graph where:
A precedence table lists activities and their immediate predecessors. It specifies the order in which activities must occur, based only on their direct dependencies.
Activity | Duration | Immediate Predecessors |
---|---|---|
A | 4 | - |
B | 6 | A |
C | 3 | A |
D | 5 | B, C |
E | 2 | D |
To derive a precedence table from an activity network:
Question Construct an activity network from the following precedence table:
Activity | Duration | Immediate Predecessors |
---|---|---|
A | 3 | - |
B | 2 | A |
C | 4 | A |
D | 5 | B, C |
E | 3 | C |
F | 6 | D, E |
Step 1**: Identify Nodes and Activities**
Step 2**: Draw Dependencies**
Step 3**: Add Start and End Nodes**
Final Activity Network
The network has a directed flow from the start node to the end node, with all dependencies and durations represented.
Incorrect Dependencies: Forgetting that precedence tables only list immediate predecessors, not all preceding activities.
Omitting Start or End Nodes: Failing to include a single start and end node in the activity network leads to an incomplete graph.
Wrong Direction of Edges: Drawing edges in the incorrect direction can misrepresent the sequence of activities.
Overlapping Dependencies: Adding unnecessary dependencies that are not specified in the precedence table.
Misinterpreting "Immediate Predecessors": Confusing indirect dependencies (e.g., ) with immediate ones.
Dependency Rule: An activity can only start after all its immediate predecessors have been completed.
Graph Flow: Activity networks flow from a single start node to a single end node.
Precedence Table Construction: For each activity:
Enhance your understanding with flashcards, quizzes, and exams—designed to help you grasp key concepts, reinforce learning, and master any topic with confidence!
70 flashcards
Flashcards on Activity Networks & Precedence Tables
Revise key concepts with interactive flashcards.
Try Further Maths Decision Maths 1 Flashcards7 quizzes
Quizzes on Activity Networks & Precedence Tables
Test your knowledge with fun and engaging quizzes.
Try Further Maths Decision Maths 1 Quizzes29 questions
Exam questions on Activity Networks & Precedence Tables
Boost your confidence with real exam questions.
Try Further Maths Decision Maths 1 Questions27 exams created
Exam Builder on Activity Networks & Precedence Tables
Create custom exams across topics for better practice!
Try Further Maths Decision Maths 1 exam builder50 papers
Past Papers on Activity Networks & Precedence Tables
Practice past papers to reinforce exam experience.
Try Further Maths Decision Maths 1 Past PapersDiscover More Revision Notes Related to Activity Networks & Precedence Tables to Deepen Your Understanding and Improve Your Mastery
Join 500,000+ A-Level students using SimpleStudy...
Join Thousands of A-Level Students Using SimpleStudy to Learn Smarter, Stay Organized, and Boost Their Grades with Confidence!
Report Improved Results
Recommend to friends
Students Supported
Questions answered