Revision notes with simplified explanations to understand Dummy Activities quickly and effectively.
435+ students studying
Dummy activities are used in activity networks to represent dependencies that cannot otherwise be captured due to shared relationships between activities. They are essential for ensuring the logical correctness of an activity network while preserving clarity.
For example, if B depends on A, but C depends on A and B, a dummy is required to differentiate these dependencies.
To Ensure Logical Flow Keeps the network consistent with the precedence table by explicitly showing all dependencies.
To Avoid Ambiguity Prevents multiple activities from having identical start and end nodes, which could make it unclear which dependencies apply.
Question Consider the following precedence table:
Activity | Duration | Immediate Predecessors |
---|---|---|
A | 3 | - |
B | 2 | A |
C | 4 | A |
D | 5 | B, C |
Step 1: Initial Network Construction
Step 2: Identify Dummy Requirement
Step 3: Add the Dummy Activity
Final Network
Forgetting to Add Dummies Omitting necessary dummy activities leads to ambiguous or incorrect networks.
Improper Dummy Placement Placing a dummy where it does not resolve dependency conflicts can confuse the network logic.
Incorrect Interpretation Misinterpreting dummy activities as real tasks with duration or resource requirements.
Ignoring Precedence Relationships Failing to include all required dependencies in the activity network.
Redundant Dummies Adding unnecessary dummy activities that do not resolve ambiguity.
Enhance your understanding with flashcards, quizzes, and exams—designed to help you grasp key concepts, reinforce learning, and master any topic with confidence!
70 flashcards
Flashcards on Dummy Activities
Revise key concepts with interactive flashcards.
Try Further Maths Decision Maths 1 Flashcards7 quizzes
Quizzes on Dummy Activities
Test your knowledge with fun and engaging quizzes.
Try Further Maths Decision Maths 1 Quizzes29 questions
Exam questions on Dummy Activities
Boost your confidence with real exam questions.
Try Further Maths Decision Maths 1 Questions27 exams created
Exam Builder on Dummy Activities
Create custom exams across topics for better practice!
Try Further Maths Decision Maths 1 exam builder50 papers
Past Papers on Dummy Activities
Practice past papers to reinforce exam experience.
Try Further Maths Decision Maths 1 Past PapersDiscover More Revision Notes Related to Dummy Activities to Deepen Your Understanding and Improve Your Mastery
96%
114 rated
Critical Path Analysis
Activity Networks & Precedence Tables
370+ studying
185KViewsJoin 500,000+ A-Level students using SimpleStudy...
Join Thousands of A-Level Students Using SimpleStudy to Learn Smarter, Stay Organized, and Boost Their Grades with Confidence!
Report Improved Results
Recommend to friends
Students Supported
Questions answered