Resource levelling is the process of redistributing activities within a project's timeline to reduce fluctuations in resource usage while ensuring the project's completion time is not exceeded. This is particularly useful when worker availability is limited or uneven resource demand leads to inefficiencies.
Resource levelling builds upon resource histograms by adjusting the timing of non-critical activities (those with float) to smooth resource demand.
Non-critical activities can be rescheduled within their float to achieve a smoother resource histogram. The adjustments must:
Step 1: Given Information
The project consists of the following activities:
Activity | Duration (days) | Workers Required | Start Time | Float |
---|---|---|---|---|
A | 3 | 2 | 0 | 0 |
B | 4 | 3 | 3 | 2 |
C | 2 | 4 | 7 | 3 |
D | 3 | 1 | 5 | 5 |
Worker Availability: 5 workers.
Step 2: Initial Resource Histogram
Using the given start times:
Day: 0 1 2 3 4 5 6 7 8 9 10
Activity A ███
Activity B ████
Activity D ███
Activity C ██
Workers: 2 2 2 3 3 4 4 4 4 1 1
Step 3: Identify Peaks
The highest demand is 4 workers on days 5–8, but there are 5 workers available. This is acceptable, but the resource histogram can still be levelled to smooth the demand.
Step 4: Adjust Non-Critical Activities
Revised schedule:
Day: 0 1 2 3 4 5 6 7 8 9 10
Activity A ███
Activity B ████
Activity D ███
Activity C ██
Workers: 2 2 2 3 3 3 3 1 1 1 1
Step 5: Evaluate the Smoothed Histogram
The new histogram has fewer peaks, achieving more consistent worker utilization:
Step 1: Given Information
The project consists of the following activities:
Activity | Duration (weeks) | Workers Required | Start Time | Float |
---|---|---|---|---|
A | 2 | 5 | 0 | 0 |
B | 3 | 4 | 2 | 1 |
C | 2 | 3 | 4 | 2 |
D | 1 | 2 | 5 | 2 |
Worker Availability: 8 workers.
Step 2: Initial Resource Histogram
Week: 0 1 2 3 4 5 6 7
Activity A █████
Activity B ████
Activity C ███
Activity D ██
Workers: 5 5 9 7 7 5 2 0
The total demand exceeds 8 workers in week 2.
Step 3: Adjust Non-Critical Activities
Revised schedule:
Week: 0 1 2 3 4 5 6 7
Activity A █████
Activity B ████
Activity C ███
Activity D ██
Workers: 5 5 5 7 7 5 2 0
Step 4: Evaluate the Smoothed Histogram
Enhance your understanding with flashcards, quizzes, and exams—designed to help you grasp key concepts, reinforce learning, and master any topic with confidence!
70 flashcards
Flashcards on Resource Levelling
Revise key concepts with interactive flashcards.
Try Further Maths Decision Maths 1 Flashcards7 quizzes
Quizzes on Resource Levelling
Test your knowledge with fun and engaging quizzes.
Try Further Maths Decision Maths 1 Quizzes29 questions
Exam questions on Resource Levelling
Boost your confidence with real exam questions.
Try Further Maths Decision Maths 1 Questions27 exams created
Exam Builder on Resource Levelling
Create custom exams across topics for better practice!
Try Further Maths Decision Maths 1 exam builder50 papers
Past Papers on Resource Levelling
Practice past papers to reinforce exam experience.
Try Further Maths Decision Maths 1 Past PapersDiscover More Revision Notes Related to Resource Levelling to Deepen Your Understanding and Improve Your Mastery
96%
114 rated
Critical Path Analysis
Activity Networks & Precedence Tables
340+ studying
199KViewsJoin 500,000+ A-Level students using SimpleStudy...
Join Thousands of A-Level Students Using SimpleStudy to Learn Smarter, Stay Organized, and Boost Their Grades with Confidence!
Report Improved Results
Recommend to friends
Students Supported
Questions answered