Network analysis definition

Technique to find most time-efficient way to complete a project

Critical path

Sequence of tasks with no gaps to complete project fastest

Critical activities

Activities on critical path; delays affect whole project

What nodes show in network diagrams

Where one activity stops and another begins

3 parts of a node

Node number (left), EST (top-right), LFT (bottom-right)

When node is on critical path

When EST and LFT are the same

How to calculate EST

Add previous activity's duration to its EST

How LFT is calculated

Work backwards; subtract next activity's duration from its LFT

Float time definition

Spare time available for an activity (only non-critical)

Float time formula

LFT - duration - EST

Explore AQA A-Level Business Revision Notes by Topics

Explore AQA A-Level Business Model Answers by Topics

Explore AQA A-Level Business Quizzes by Topics

Explore AQA A-Level Business Exam Questions by Topics

Join 100,000+ A-Level students studying Flashcards with us.

Select your subjects, and get access to A+ resources today.