What is the main purpose of network analysis in project management?

To determine the quickest way to finish tasks

In network analysis, what does step 3 of the four-step process involve?

Arranging activities as a network or graph

What happens if a critical activity is delayed?

The whole project is delayed

What three parts make up a node in a network diagram?

Node number, EST, and LFT

What is the EST (earliest start time) of the very first activity in any project?

0

What is the formula for calculating total float time?

LFT - duration - EST

When does a node sit on the critical path?

When EST and LFT are the same

What are dummy activities shown as on a network diagram?

Dotted lines

Which advantage allows network analysis to help with budgeting?

Cash flow forecasting

What is a key disadvantage of setting tight deadlines through network analysis?

Quality can suffer as corners are cut

Explore AQA A-Level Business Revision Notes by Topics

Explore AQA A-Level Business Model Answers by Topics

Explore AQA A-Level Business Flashcards by Topics

Explore AQA A-Level Business Exam Questions by Topics

Join 100,000+ A-Level students studying Quizzes with us.

Select your subjects, and get access to A+ resources today.