10 cards from this deck
Technique to find most time-efficient way to complete a project
Sequence of tasks with no gaps to complete project fastest
Activities on critical path; delays affect whole project
Where one activity stops and another begins
Node number (left), EST (top-right), LFT (bottom-right)
When EST and LFT are the same
Add previous activity's duration to its EST
Work backwards; subtract next activity's duration from its LFT
Spare time available for an activity (only non-critical)
LFT - duration - EST