Resource Levelling (Edexcel A-Level Further Mathematics): Flashcards
📚Flashcards
Practise the cards
10 cards from this deck
ShowHide
Practise the cards
10 cards from this deck
Definition of resource levelling
Definition of resource levelling
Redistributing activities within project timeline to smooth resource usage without exceeding project completion time
Float of critical activities
Float of critical activities
Zero (no float)
Can non-critical activities be delayed
Can non-critical activities be delayed
Yes, within their float
Key objective of resource levelling
Key objective of resource levelling
Minimise peaks and troughs in resource usage
What resource levelling must retain
What resource levelling must retain
Original project duration
Formula for total float
Formula for total float
Resource levelling constraint
Resource levelling constraint
at any time
Effect of adjusting critical activities
Effect of adjusting critical activities
Delays the project
What must be preserved when adjusting activities
What must be preserved when adjusting activities
Order of dependencies
Max start time for adjusted non-critical activity
Max start time for adjusted non-critical activity
Latest possible start time