10 cards from this deck
Redistributing activities within project timeline to smooth resource usage without exceeding project completion time
Zero (no float)
Yes, within their float
Minimise peaks and troughs in resource usage
Original project duration
Float=LFT−EST−Duration\text{Float} = \text{LFT} - \text{EST} - \text{Duration}Float=LFT−EST−Duration
Total workers≤Available workers\text{Total workers} \leq \text{Available workers}Total workers≤Available workers at any time
Delays the project
Order of dependencies
Latest possible start time