Resource Levelling (Edexcel A-Level Further Mathematics): Quizzes
📚Quizzes
Practise the questions
10 questions from this quiz
ShowHide
Practise the questions
10 questions from this quiz
What is resource levelling?
What is resource levelling?
Redistributing activities to reduce usage peaks
Which activities can be adjusted during resource levelling?
Which activities can be adjusted during resource levelling?
Non-critical activities only
How much float do critical activities have?
How much float do critical activities have?
No float
What must resource levelling retain?
What must resource levelling retain?
Original project duration
What limit must adjusted start times not exceed?
What limit must adjusted start times not exceed?
Latest possible start time
In Example 1, how many workers were available?
In Example 1, how many workers were available?
5 workers
In Example 2, what was the total demand in week 2 initially?
In Example 2, what was the total demand in week 2 initially?
9 workers
Why should critical activities not be adjusted?
Why should critical activities not be adjusted?
Rescheduling them delays the project
What is the levelling constraint for total workers?
What is the levelling constraint for total workers?
Total workers available workers
What characteristic allows non-critical activities to be delayed?
What characteristic allows non-critical activities to be delayed?
They have float
