Critical Path Analysis (Leaving Cert Applied Maths): Flashcards
Practise the cards
14 cards from this deck
ShowHide
Practise the cards
14 cards from this deck
Critical Path Analysis (CPA)
Critical Path Analysis (CPA)
Project management technique to plan complex projects by determining the most efficient sequence of activities
Main purpose of CPA
Main purpose of CPA
Identify which activities must finish before others can begin
Precedence table
Precedence table
Two-column table listing activities and their dependencies
Starter activities marking
Starter activities marking
Marked with dash (-), have no dependencies
Activity network
Activity network
Visual diagram showing how project activities connect together
Nodes in activity network
Nodes in activity network
Numbered circles representing project milestones or stages
Arrows in activity network
Arrows in activity network
Show flow and direction between activities
Source node
Source node
Starting point where entire project begins
Sink node
Sink node
Final point where project ends
How to identify sink node
How to identify sink node
Activities not appearing as dependencies for other activities
Dummy variables in CPA
Dummy variables in CPA
Special connections shown as dashed lines in network diagram
Dummy variables represent
Dummy variables represent
Logical relationships, not actual work or time
When to use dummy variables
When to use dummy variables
When activities have complex dependencies or to avoid double arrows between same nodes
First activities for building network
First activities for building network
Activities with no dependencies (source activities)