What is the main purpose of Critical Path Analysis?

Identify most efficient sequence

How are starter activities marked in a precedence table?

With a dash (-)

What does a precedence table list?

Activities and their dependencies

What do numbered circles represent in an activity network?

Project milestones or stages

What do arrows show in an activity network?

Flow and direction between activities

What is a source node?

The starting point of the project

How can you identify the sink node from a precedence table?

Activities not appearing as dependencies

How are dummy variables shown in activity networks?

As dashed lines

What do dummy variables represent?

Logical relationships, not actual work

When are dummy variables needed?

To avoid double arrows between nodes

What should you start with when building an activity network?

Activities with no dependencies

In which field is CPA particularly valuable?

Construction

Explore Leaving Cert Applied Maths Revision Notes by Topics

Explore Leaving Cert Applied Maths Model Answers by Topics

Explore Leaving Cert Applied Maths Flashcards by Topics

Explore Leaving Cert Applied Maths Exam Questions by Topics

Join 100,000+ Leaving Cert students studying Quizzes with us.

Select your subjects, and get access to A+ resources today.