What is the main purpose of Critical Path Analysis?
What is the main purpose of Critical Path Analysis?
Identify most efficient sequence
How are starter activities marked in a precedence table?
How are starter activities marked in a precedence table?
With a dash (-)
What does a precedence table list?
What does a precedence table list?
Activities and their dependencies
What do numbered circles represent in an activity network?
What do numbered circles represent in an activity network?
Project milestones or stages
What do arrows show in an activity network?
What do arrows show in an activity network?
Flow and direction between activities
What is a source node?
What is a source node?
The starting point of the project
How can you identify the sink node from a precedence table?
How can you identify the sink node from a precedence table?
Activities not appearing as dependencies
How are dummy variables shown in activity networks?
How are dummy variables shown in activity networks?
As dashed lines
What do dummy variables represent?
What do dummy variables represent?
Logical relationships, not actual work
When are dummy variables needed?
When are dummy variables needed?
To avoid double arrows between nodes
What should you start with when building an activity network?
What should you start with when building an activity network?
Activities with no dependencies
In which field is CPA particularly valuable?
In which field is CPA particularly valuable?
Construction