12 cards from this deck
Visual tool showing activity network as a timeline with durations and float time
Horizontal bar chart
Zero total float time
Delays entire project by the same duration
Time an activity can be delayed without affecting project completion
Late Time−Early Time−Duration\text{Late Time} - \text{Early Time} - \text{Duration}Late Time−Early Time−Duration
At the top, shown as solid bars
Dashed line extensions
Activity's duration
Float time available
Identify the critical path by calculating total float
Activities that must be happening at that time