Stock Control Problems (Leaving Cert Applied Maths): Quizzes

📚Quizzes
Stock Control Problems
Sign up to keep practising.Create a free account to play more quizzes and track your progress.

Practise the questions

12 questions from this quiz

Show

What technique does stock control use to find optimal solutions?

Backward induction

How many components are in the total cost formula?

Four

In the example, what is the storage cost per scooter per month?

€40

What are overhead costs per month when production occurs?

€200

Above how many units must an assistant be hired?

3 units

What is the hired labour cost when production exceeds capacity?

€350

Which column is NOT in the decision table structure?

Revenue

Where should you begin the backward induction process?

The final month

How is the cost for any decision calculated?

Immediate cost + optimal future cost

What is the maximum storage capacity in the example?

3 scooters

What is the formula for Overall Profit?

Revenue−Total Costs−Fixed Costs\text{Revenue} - \text{Total Costs} - \text{Fixed Costs}

What is the first step in finding the optimal solution?

Marking feasible options

Explore Leaving Cert Applied Maths Revision Notes by Topics

Explore Leaving Cert Applied Maths Model Answers by Topics

Explore Leaving Cert Applied Maths Flashcards by Topics

Explore Leaving Cert Applied Maths Exam Questions by Topics

Join 100,000+ Leaving Cert students studying Quizzes with us.

Select your subjects, and get access to A+ resources today.