Critical Paths / Activities (Leaving Cert Applied Maths): Flashcards
📚Flashcards
Practise the cards
15 cards from this deck
ShowHide
Practise the cards
15 cards from this deck
Early time definition
Early time definition
Earliest possible moment an event can occur (all previous activities complete)
Late time definition
Late time definition
Latest moment an event can occur without causing project delay
Forward pass purpose
Forward pass purpose
Calculate early times from start to finish
Backward pass purpose
Backward pass purpose
Calculate late times from finish to start
Source node
Source node
Starting point of project
Sink node
Sink node
End point of project
Convergence rule (forward pass)
Convergence rule (forward pass)
Take largest early time value
Divergence rule (backward pass)
Divergence rule (backward pass)
Take smallest late time value
Total float
Total float
How much an activity can be delayed without affecting project completion
Total float formula
Total float formula
Variables in
Variables in
=late end, =early start, =duration
Critical activity
Critical activity
Activity with zero total float
Critical path
Critical path
Sequence of critical activities from start to finish
Critical path determines
Critical path determines
Minimum project duration
Late time at sink node
Late time at sink node
Equals early time