Critical Paths / Activities (Leaving Cert Applied Maths): Flashcards

📚Flashcards
Critical Paths / Activities
Sign up to keep revising.Create a free account to study more flashcards and track your progress.

Practise the cards

15 cards from this deck

Show

Early time definition

Earliest possible moment an event can occur (all previous activities complete)

Late time definition

Latest moment an event can occur without causing project delay

Forward pass purpose

Calculate early times from start to finish

Backward pass purpose

Calculate late times from finish to start

Source node

Starting point of project

Sink node

End point of project

Convergence rule (forward pass)

Take largest early time value

Divergence rule (backward pass)

Take smallest late time value

Total float

How much an activity can be delayed without affecting project completion

Total float formula

d−a−td - a - t

Variables in d−a−td - a - t

dd=late end, aa=early start, tt=duration

Critical activity

Activity with zero total float

Critical path

Sequence of critical activities from start to finish

Critical path determines

Minimum project duration

Late time at sink node

Equals early time

Explore Leaving Cert Applied Maths Revision Notes by Topics

Explore Leaving Cert Applied Maths Model Answers by Topics

Explore Leaving Cert Applied Maths Quizzes by Topics

Explore Leaving Cert Applied Maths Exam Questions by Topics

Join 100,000+ Leaving Cert students studying Flashcards with us.

Select your subjects, and get access to A+ resources today.