Earliest possible moment an event can occur (all previous activities complete)
Latest moment an event can occur without causing project delay
Calculate early times from start to finish
Calculate late times from finish to start
Starting point of project
End point of project
Take largest early time value
Take smallest late time value
How much an activity can be delayed without affecting project completion
d−a−td - a - td−a−t
ddd=late end, aaa=early start, ttt=duration
Activity with zero total float
Sequence of critical activities from start to finish
Minimum project duration
Equals early time